The Joint Strategic Committee is recommended to: I. noted the progress on the schemes; II. approved the release of £235,000 from the development budget to progress work on the Small Sites Programme; III. delegated authority to the Director for Communities, following a tender process, to award the contract for design and consultancy services in respect of the Small Sites Programme; IV. noted that a further report would be presented in February 2020 updating members on the final cost of Cecil Norris development, and detailing the outcome of the tender pr approved the release of £235,000 from the development budget to progress work on the Small Sites Programme;ocess for Albion Street together with the associated updated budget requirements. Call In: The call-in deadline for this decision will be 5.00pm on 24 January 2020.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1To update Executive Members on the current progress of the housing development programme across the two Council areas, and the next steps in regards to the small sites programme (Hidden Homes).
1.2To seek approval for the release of funding for the Small Sites Programme.
Recommendations
2.1The Joint Strategic Committee is recommended to:
i) To note progress on the schemes; ii) To approve the release of £235,000 from the development budget to progress work on the Small Sites Programme; iii) To delegate authority to the Director for Communities, following a tender process, to award the contract for design and consultancy services in respect of the Small Sites Programme. iv) To note that a further report will be presented in February 2020 updating members on the final cost of Cecil Norris development, and detailing the outcome of the tender process for Albion Street together with the associated updated budget requirements.
3.0Context
3.1Adur and Worthing have recently embarked on a development programme to help enable it meet the acute demand for affordable and temporary housing within Adur and Worthing.
3.2Since starting the programme, four sites have been purchased and planning consent gained to deliver 42 homes for temporary accommodation. Three further sites have also been consented to provide 49 homes within the HRA for general needs rent (affordable and social rent).
3.3Of the above 11 homes for temporary accommodation are due to be completed in 2019/20, a further 40 (temporary and within the HRA) homes homes are due for completion in 2020/21 and 52 homes in 2021/22.
3.4This report is intended to provide an update on the current status of development programme and request approvals where necessary to move schemes to their next stage.
4.0Development Programme Update
Worthing Borough Council
4.1Rowlands Road
The site was acquired for redevelopment in February 2019 . Planning was gained in August for the refurbishment of the existing building to provide 19 flats for temporary accommodation. A contractor tender has recently concluded, the Council’s advisors (RLF) have written a tender report which recommends appointing a preferred bidder. A separate Executive Member report will be issued to support the contract award for Rowlands Road with a view to starting on site in April 2020.
4.2Downview Phase 1
Downview will provide nine flats for Temporary Accommodation. The site is coming into the final phase of construction with handover scheduled for the beginning of March 2020.
4.3Downview Phase 2
Approval for the redevelopment of Downview was given in September 2019. As part of this approval delegated authority was given to ‘award all necessary associated contracts to the Head of Housing in consultation with the WBC Executive Member for Customer Service’. Tender returns for the eight flats have been received. Tenders have been moderated with a tender report currently being written. The contract sum is within budget and as such a build contract will be entered into with the winning Contractor early in 2020, with a view to starting on site shortly thereafter.
Adur District Council
4.4101 North Road
The two homes at 101 North Road have been completed and are now occupied.
4.5Cecil Norris
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.