Decision : The Joint Strategic Committee I. granted permission to install proposed vehicular exclusion measures; II. approved the creation of a budget for these works of £60,000 funded by budget virements ; III. recommended that Adur District Council, as Trustees of , note this resolution of the Joint Strategic Committee, made on behalf of the Trustees. Call In : The call-in deadline for decisions ( i ) and (ii) will be 5.00pm on 17 July 2020. There is no call-in for recommendations (iii) to meetings of Adur and Worthing Councils.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1. Purpose The purpose of this report is to request that Adur District Council, as sole trustee of Southwick Green, grants permission for the installation of vehicular exclusion measures via Joint Strategic Committee under its delegated authority to act.
Decision will require the virement of monies to fund the immediate installation of gates, bollards and benches in strategic positions around the Green to prevent unauthorised vehicular access.
Recommendations
2.1The Joint Strategic Committee is recommended to: i. Grant permission to install proposed Southwick Green vehicular exclusion measures in positions highlighted in Appendix 1. ii. Approve the creation of a budget for these works of £60,000 funded by budget virements as set out in paragraph 6.2. iii. Recommend that Adur District Council, as Trustees of Southwick Green, note this resolution of the Joint Strategic Committee, made on behalf of the Trustees. 3. Context
3.1Southwick Green has been subject to various incursions of vehicles and regular settlement over the years. These uses do not constitute using the Green for recreational purposes, and in fact are adverse to recreational use. Adur District Council as sole trustee is under a positive duty to protect the integrity of the Green and its general recreational enjoyment. It is required, therefore, that effective measures are put in place to prevent any future incursions.
4. Issues for consideration
4.1Options do exist for the exclusion works. Initial plans for strategic tree planting in 21/22 have now been altered since planting has already been maximised on the site. Gates, bollards, and benches are seen as the best, and only, possible strategy to prevent future incursion. Virement of the tree planting budget from 21/22 (£22k) is therefore requested to aid the funding of the works proposed here in 2020/21.
4.2Possible options relate to 1.5m spacing between obstacles, or 2m spacing. 1.5m spacing is recommended to minimise distances should any single object be removed by extreme force or accident.
4.3Doing nothing, as an option, would result in additional costs to the Council associated with clean-up of settlements, or remediation following unauthorised vehicle access. Members of the public would also have reduced recreational enjoyment of the space at certain times of the year.
4.4The Council assumes the role of sole trustee of Southwick Green. Joint Strategic Committee received delegated authority to act on behalf of the Council in December 2019. As such the JSC is asked to authorise the installation of the proposed Southwick Green exclusion measures in positions highlighted in appendix 1.
5. Engagement and Communication
5.1Ward member feedback has been sought, and the recommendations are very much supported. 5.2 The public were invited to an on-site drop-in meeting on site. Approximately 50 people attended and were supportive of the recommended works outlined here. Local houses received a mail drop outlining the proposals, and a further, more concentrated, local group also met to discuss the proposals; again this communicated support of the recommendations here. 5.3 The Council’s Planning Department have advised that the recommended works are permissible under Local Authority permitted development rights. Feedback?
Financial implications
6.1The cost of the works are estimated to be £60,000. There is currently no budget provision in 2020/21 to fund the costs of this proposed project.
6.2However, contained within the 2021/22 budget are some schemes which could be deferred and re-bid for in a future year, with the funding allocated for this purpose. Consequently it is proposed that the following budgets be utilised to fund the works: £ 2021/22 - Southwick Green Environmental Improvements 25,000 2021/22 - Lancing Manor Leisure Centre - Vehicle access 33,600 reconfiguration Allocation from contingency budget 1,400
Total funding 60,000
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.