The Joint Strategic Committee i. noted the progress on the schemes and approved the approach being taken; ii. noted the list of included sites set out at section 4.6 of the report, based on the feedback from the recent public consultation exercise, and agreed the amendment of the list to remove Downs Way; iii. approved the business plan; iv. recommended that Adur District Council approve the proposed capital expenditure of £15.935m from the development budget to deliver the projects funded by grant of £2.24m and prudential borrowing of £13.695m; v. any proposed substitutions or amendments to the sites within the programme, to be agreed by the Joint Strategic Committee; and vi. approved the principle of the sale of sites to aid delivery of the programme and reduce potential rents should the need arise. Delegation to be given to the Director for Communities, in consultation with the Adur District Council Executive Member for Customer Services and the Leader of Adur Council, to agree sites for disposal; vii. delegated authority to the Director for Communities, following a tender process, to award the building contracts and all associated contracts to enable delivery of the sites. Call In: The call-in deadline for decisions (i), (ii), (iii), (v), (vi) and (vii) will be 5.00pm on 16 October 2020. There is no call-in for recommendations to meetings of Adur and Worthing Councils, decision (iv).
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1To provide details of the small sites programme to Adur District Council Executive Members, which is planned to develop up to 56 new affordable homes on Council owned sites.
1.2To allow members the opportunity to comment on or remove any schemes that they consider unsuitable for further consideration following the recent consultation exercise.
1.3To seek approval for an increase to the capital programme of £15.934m funded from borrowing and external funding to enable the programme to progress.
Recommendations
2.1The joint Strategic Committee is recommended to: i) Note the progress on the schemes and approve the approach being taken.
ii) Note the list of included sites set out at section 4.6 of this report and to agree or amend this list of sites based on the feedback from the recent public consultation exercise.
iii) Approve the business plan;
iv) Recommend to Council to approve the proposed capital expenditure of £15.935 m from the development budget to deliver these projects funded by grant of £2.24m and prudential borrowing of £13.695m.
v) Delegate authority to the Director for Communities to substitute or amend sites within the programme, should any of the sites be deemed unsuitable for development once through the initial due diligence and planning stage. Any substitution to be within the agreed budget and funding within this paper and to be agreed in consultation with the Adur District Council Executive Member for Customer Services and the Leader of Adur Council.
vi) Approve the principle of the sale of sites to aid delivery of the programme and reduce potential rents should the need arise. Delegation to be given to the Director for Communities, in consultation with the Adur District Council Executive Member for Customer Services and the Leader of Adur Council, to agree sites for disposal.
vii) Delegate authority to the Director for Communities, following a tender process, to award the building contracts and all associated contracts to enable delivery of the sites. 3. Context
3.1As part of ‘Platforms for Our Places - Going Further’ adopted by Adur District Council (ADC) in December 2019, Members have committed to the ongoing focus on delivering new affordable homes across the District as part of the Housing Revenue Account (HRA) development programme. The small sites programme forms part of this and is expected to deliver 56 new rented Council owned homes.
3.2It is well documented that across the Adur District and indeed across the South of England, there is a pressing and urgent need for more truly affordable accommodation. The Council currently has over 700 households on its housing register waiting for affordable rented accommodation and over 40 households in temporary accommodation who need suitable housing. The Council has responded proactively by identifying a number of opportunities to develop new homes on Council owned land.
3.3One of the three key objectives in Adur and Worthing Councils’ Housing Strategy 2020-2023, is ‘Improving the levels of affordable housing supply’. The development strategy which demonstrates how this will be achieved has an objective to ‘utilise the Council’s land and housing stock for self delivery’. This proposal contributes to the delivery of this objective by providing affordable homes on Council owned land.
3.4Following an initial report prepared by consultants Baily Garner in 2018, which reviewed 40 garage and other small site sites owned by Adur Homes, ten suitable sites were identified.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.