The Joint Strategic Committee: 1) approved the Full Business Case for the Worthing Integrated Care Centre and Multi Storey Car Park; 2) recommended that Worthing Borough Council release the full budget for the construction of the integrated care centre funded through borrowing subject to final agreement of the Heads of Terms for the occupier leases, acquisition of Central Clinic and the development agreement (£33,971,000); 3) delegated authority to the Head of Major Projects & Investment to: a. appoint through West Sussex Estate Partnership the most advantageous construction contractor to deliver the WICC and 2 MSCP; b . execute occupier lease and service level agreements for the occupation of the WICC facility; c . authorise the acquisition of the Central Clinic; d . execute a Development Agreement with West Sussex (Worthing) Limited; e . authorise temporary NHS services to operate in Liverpool Gardens Car Park on the site of the former Shopmobility building; f . agree the acquisition of Shelley Road Medical Centre and Heene Road Surgery, supporting future housing delivery options and subject to business case approval; and g . make any further necessary consultancy appointments to execute the delivery of the scheme. Call In: The call-in deadline for decisions 1 and 3 ( a to g) will be 5.00pm on 12 April 2021. There is no call-in for recommendations (2) to Adur and Worthing Councils.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1. Purpose 1.1 The report seeks approval of the formal Full Business Case (FBC) for the Worthing Integrated Care Centre (WICC) and Multi Storey Car Park (MSCP) development scheme on Worthing Town Hall Car Park. This will enable contracts and agreements to be executed and for the project to be delivered.
2. Recommendations The Joint Strategic Committee is recommended to:
2.1Approve the Full Business Case for the Worthing Integrated Care Centre and Multi Storey Car Park.
2.2Recommend to Full Council to release the full budget for the construction of the integrated care centre funded through borrowing subject to final agreement of the Heads of Terms for the occupier leases, acquisition of Central Clinic and the development agreement (£33,971,000)
2.3Delegate authority to the Head of Major Projects & Investment to: a. To appoint through West Sussex Estate Partnership the most advantageous construction contractor to deliver the WICC and
1 MSCP. b. Execute occupier lease and service level agreements for the occupation of the WICC facility. c. Authorise the acquisition of the Central Clinic. d. Execute a Development Agreement with West Sussex (Worthing) Limited. e. Authorise temporary NHS services to operate in Liverpool Gardens Car Park on the site of the former Shopmobility building. f. Agree the acquisition of Shelley Road Medical Centre and Heene Road Surgery, supporting future housing delivery options and subject to business case approval. g. Make any further necessary consultancy appointments to execute the delivery of the scheme.
Background
3.1At the Joint Strategic Committee meeting of 10th October 2017, members approved a report to progress a health related development scheme at Worthing Town Hall Car Park. The site, owned by Worthing Borough Council, has been considered an underutilised key brownfield development site and the opportunity for development was recognised in the Worthing Investment Prospectus.
3.2A Master Plan for the new facility was initially produced through an options appraisal process. The council set out to develop an Outline Business Case (OBC) to prepare plans for an integrated care centre facility with NHS partners. The proposed development would bring together Coastal West Sussex CCG, Worthing Medical Group, Sussex Community Foundation Trust, and Sussex Partnership Foundation Trust services into one integrated health care facility in the heart of Worthing.
3.3The key objectives of the intervention were to improve the level of care for Worthing residents by enabling more integrated working between different parts of the NHS by co-location, and to provide a significant improvement on their existing accommodation which is dispersed throughout Worthing. The new centre would be the first of its type in Worthing and would deliver significant benefits in care for the local community.
3.4The proposed development being consistent with the strategic direction of NHS England to promote New Models of Care and Integrated Care Systems and ‘Platforms for our Places’ which set out a commitment to “partner with local health providers to deliver a health hub facility with new models of health provision”.
2 3.5 At the Joint Strategy Committee (JSC) on 7 November 2019 the committee approved the Outline Business Case (OBC) for the WICC. The committee further authorised officers to undertake the following next step in the development of the scheme:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies