Decision The Joint Strategic Committee I) noted the progress and revised approach for delivery of the Worthing Coastal Protection Scheme; II) recommended that Worthing Council amend the 2021/22 Capital Investment Programme to include the revised Phase 1 capital project for structural works to the groynes and shingle nourishment work; and III) approved the delegation to the Head of Facilities & Technical Services in consultation with the Executive Member for Regeneration to enter a Memorandum of Understanding (MoU) with the Environment Agency, following Phase 1, to commence works on revisiting the Strategic Outline Case (SOC) for the Phase 2 larger scale groyne replacement scheme. Call In : The call-in deadline for decisions I and III will be 5.00pm on 17 September 2021. There is no call-in for recommendation II to Worthing Council.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1This report provides an update to members on the revised approach to the Worthing Coastal Protection Scheme following the Environment Agency (EA) peer review of the submitted Outline Business Case (OBC) and subsequent consultation with Senior WBC Officers.
1.2The revised approach will amend the implementation of a large scale coast protection scheme for the Worthing frontage in favour of a two phased approach; a more immediate capital maintenance project (Phase 1) to repair and extend the life of existing groynes as well as shingle beach nourishment in the Town Centre area, followed by revisiting the Strategic Outline Case (SOC) for a larger scale groyne replacement scheme (Phase2) within ten years time.
Recommendations
2.1The Joint Strategic Committee is asked to:
● Note the progress and revised approach for delivery of the Worthing Coastal Protection Scheme; ● Recommend to the Council to amend the 2021/22 Capital Investment Programme to include the revised Phase 1 capital project for structural works to the groynes and shingle nourishment work.
● Approve the delegation to the Head of Facilities & Technical Services in consultation with the Executive Member for Regeneration to enter a Memorandum of Understanding (MoU) with the Environment Agency, following Phase 1, to commence works on revisiting the Strategic Outline Case (SOC) for the Phase 2 larger scale groyne replacement scheme.
Background
3.1Worthing Borough Council (WBC) is the Coast Protection Authority (CPA) for the Worthing frontage between Ferring to the west and Lancing to the east. Leading on coastal erosion risk management activities and carrying out coast protection work (including constructing and maintaining defences), shared responsibility for developing Shoreline Management Plans (SMPs) with neighbouring coastal authorities, which provide a long term holistic framework for managing the risk of coastal change.
3.2The Beachy Head to Selsey Bill SMP identifies that the frontage at Worthing consists of a wide sandy lower beach and a narrow shingle upper beach. The coast is protected by a groyne field, mostly constructed of timber, but with some more recently constructed in rock. There are also concrete splash walls and rock revetments along the frontage; however the shingle beach is the principal coastal defence.
3.3The River Arun to Adur Flood and Erosion Management Strategy was completed and approved by the Environment Agency’s Large Project Review Group (LPRG) in 2011. It categorises the frontage under the ‘Hold the Line - Sustain’ policy, meaning that the current defences need to be strengthened to keep the levels of flood and erosion risk the same as it is now. It states that the approximate number of properties at risk from flooding and erosion if defences are not maintained in 100 years’ time would total 2030 within Worthing.
3.4In 2016 WBC commissioned expert Consultants Mott MacDonald (MM) to assist them with the preparation of an initial Outline Business Case (OBC) for the beach frontage between the Ferring Rife in Arun District and Navarino Road in Worthing to reconstruct failed and ‘at end of life’ groynes across the frontage. Subsequent reviews incorporated Navarino Road to Brooklands and removed the Arun District section.
3.5An OBC provides the rationalisation behind the Technical, Strategic, Financial, Commercial, environmental and economic impacts of the proposals identifying outcome measures in accordance with the current Environment Agency Flood and Coastal Erosion Risk Management (FCERM) appraisal guidance and Grant in Aid (GiA) criteria. GiA is the amount of Partnership funding the Government through the Environment Agency (EA) contributes to the project; any shortfall in funding will have to be met by external contributions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.