Adur District Council / Worthing Borough Council
Joint Strategic Committee, Thursday 7 October 2021 at 6.30pm

Southwick Estate Consultation

Approved Committee 1 paper

Joint Strategic Committee approved this item on Thursday 7 October 2021. Below is the council's own wording, with the papers it was decided on.

ItemJSC/46/21-22

Resolved

Decision The Joint Strategic Committee: I. approved funding of £454,100 to conduct stages 2 and 3 of the engagement and options development work on the future of the estate funded from the new development and acquisition reserve; II. delegated authority to the Head of Major Projects & Investment to enter into any contracts necessary for the appointments above within the allocated budget; and III. noted that following stage 3, a further report would be presented to the Joint Strategic Committee to consider project progress and determine a preferred option. Call In : The call-in deadline for decision will be 5.00pm on 18 October 2021.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

This paper provides an update on the Southwick engagement work that has taken place so far, and seeks approval and funding to proceed with the full Options Appraisal (Stages 2 and 3).

As set out in the previous paper dated 31st March 2021, improving the homes on the Southwick Estate has been identified as a priority that aligns to Adur’s objectives. Significant work and investment was identified as being required to refurbish the blocks to a decent homes standard. The cost of refurbishment works was initially calculated as being comparable to the cost of redevelopment, with the latter having the potential to deliver significant wider benefits. Following review of the first paper, approval and funding was granted for the first stage of an engagement process to help understand what residents want.

This first engagement event has now taken place and was positively received by residents, who had a range of views on the estate and were keen to engage further as part of an Options Appraisal process. Other positive progress includes the appointment of a Resident Working Group, as well as several Independent Resident Advisor candidates being ready to be interviewed by residents.

The main stage of the Options Appraisal process (stages 2 and 3) would involve reviewing options ranging from simple refurbishment, improvements, partial redevelopment, infill and full redevelopment. The process would run from winter 2022 with an outcome targeted for summer 2022.

A project team will be required to run the options appraisal process, conduct technical work that sits behind the options and engage with residents. Approval is therefore sought for £454,100 of funding to appoint the project team, as well as to continue with the Options Appraisal.

1. Purpose

1.1To update members on the initial engagement with Southwick Estate residents to improve housing standards in the area.

1.2To agree to continue to engage with residents and leaseholders to conduct a full options appraisal to identify the best way forward for the estate.

Recommendations

The Joint Strategic Committee is requested to:

2.1Approve funding of £454,100 to conduct stages 2 and 3 of the engagement and options development work on the future of the estate funded from the new development and acquisition reserve.

2.2Delegate to the Head of Major Projects & Investment to enter into any contracts necessary for the appointments above within the allocated budget.

2.3Note that following stage 3, a further report will be presented to the Joint Strategic Committee to consider project progress and determine a preferred option.

3. Context

3.1Overview of the Estate

3.1.1. The Southwick estate is located adjacent to Southwick train station and comprises 13 blocks, owned and managed by Adur Homes, across 3 parcels of land as well as 2 commercial properties owned by third parties. 3.1.2. There are currently 248 homes across the estate with c.70% residents and 30% leaseholders. 3.2. Previous Approvals

3.2.1. The previous Southwick JSC paper dated 31st March 2021 provided a background to the rationale and history behind the Southwick Estate project. This paper noted the Council’s ambition and policies to enable residents to thrive, including providing high quality homes.

3.2.2. The paper also noted the significant investment that is required to bring the homes on the Southwick Estate to modern standards. The paper set out initial costings for refurbishment works that had been obtained, noting that analysis identified that redevelopment would have a broadly comparable cost to refurbishment while potentially offering many wider benefits. On this basis, engagement with residents was proposed to identify the best way forward and ensure residents have high quality homes into the future.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Southwick Estate ConsultationReport 977 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
NT
Neil TerrySecretary, expected
DH
Councillor Daniel HumphreysChairman, present
NP
Councillor Neil ParkinAdur Member, present
AD
Councillor Angus DunnAdur Member, present
KJ
Councillor Kevin JenkinsWorthing Member, present
CA
Councillor Carson AlburyAdur Member, present
BB
Councillor Brian BoggisAdur Member, absent
KB
Councillor Kevin BoramAdur Member, absent
EC
Councillor Edward CrouchWorthing Member, absent
EE
Councillor Emma EvansAdur Member, present
SM
Councillor Sean McDonaldWorthing Member, present
DH
Councillor Dr Heather MercerWorthing Member, present

All 13 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Southwick Estate ConsultationThis decision
  2. Acquisition of leasehold properties on the Southwick Estate to support estate improvementApproved
  3. Southwick Estate - Interim Works PackageDecided
  4. Supporting our Communities to Thrive: The Southwick Estate, Whiterock PlaceApproved

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies