Decision The Cabinet: a) Considered the General Fund Capital Investment Programmes for 2023/24 and confirms the schemes to be included as detailed in Appendix 2 and 3; b) Recommend the full programme detailed at Appendix 3 for approval by Council on the 23rd February 2023; c) Notes the amendments and additions to the reserve lists as detailed in Appendix 5 approved the Housing Revenue Account estimates for 2022/23 as set out in Appendix 1; Reason for Decision To protect and maintain the District’s Assets Alternative options considered As outlined in the report. Call In The call in deadline for this decision is Tuesday 14 February 2023 at 5.00pm. There is no call in for b) as it is a decision for Council
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1This report recommends the investment programmes for Adur District Council which supports both the strategic ambition of the Council, and the vital regular investment toward the upkeep and improvement of our public assets and the delivery of services.
1.2Members are now asked to approve the new schemes for 2023/24. This report recommends:
● the schemes for inclusion in the overall Capital Investment Programmes for 2023/24; and
● an indicative list of schemes for 2024/25 which will be confirmed next year.
1.3The report also informs the Cabinet of the resources available for future capital investment, and updates Members about the financing of the proposed programmes.
1.4The following appendices have been attached to this report:
(i) Appendix 1 2022/23 Budgets reprofiled to 2023/24 for scheme delivery in 2023/24; (ii) Appendix 2 New schemes to be included in 2023/24 Capital Investment Programme including the share of the Joint Strategic Committee programme; (iii) Appendix 3 Full Adur District Council capital investment programme for 2022/23 - 2025/26 (iv) Appendix 4 Partnership capital investment programme for 2023/24 - 2025/26
(v) Appendix 5 Amendments and additions to the Reserve List of schemes
Recommendations
2.1The Cabinet is recommended to:
(a) Consider the General Fund Capital Investment Programmes for 2023/24 and confirm the schemes to be included as detailed in Appendix 2 and 3;
(b) Recommend the full programme detailed at Appendix 3 for approval by Council on the 23rd February 2023;
(c) Note the amendments and additions to the reserve lists as detailed in Appendix 5
3. Context
3.1The development of the capital programme is guided by the Capital Strategy which outlines the level of resources available and sets the framework for the approval and delivery of the programme. The Adur and Worthing Capital Strategy 2023 - 26 was updated and agreed by the Joint Strategic Committee (JSC) on 11th October 2022. The financial impact of the proposed Capital Investment Programme was set out in the outline 5 year forecast included in the “Developing a revenue budget for 2023/24 against a backdrop of high inflation” report which was agreed by Joint Strategic Committee on 5th July 2022 and subsequently refreshed in the budget update report considered in December.
3.2The Capital and Budget Strategies set out the following:
(a) A maximum level of funding available per year for the next 5 years to fund new General Fund schemes was to be limited to £1.0m in 2023/24; (b) £5.6m was to be invested annually into the Housing Investment Programme which excludes any new developments which can be justified on a self-funding basis.
(c) The Budget Strategy highlighted concerns about affordability in the medium term. Members of the Council were made aware that the number, age and condition of Council’s assets continue to be a cause for concern. The funding of the programmes is to consist of prudential borrowing, capital grants, revenue/reserve funding and capital receipts.
(c) Additional capital expenditure will only be agreed where additional funding from capital grants, contributions, earmarked receipts, approved additional prudential borrowing or use of reserves has been secured.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Revenue Account: 2026/27 BudgetDecision 1. That the Housing Revenue Account estimates for 2026/27 as set out in Appendix 1 be approved 2. That it be...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.