Redevelopment of 24 Marine Place Worthing to provide Temporary Accommodation
ApprovedCommittee1 paper
Joint Strategic Sub-Committee (Worthing) approved this item on Tuesday 13 June 2023. Below is the council's own wording, with the papers it was decided on.
Decision The Worthing Sub Committee of the Joint Strategic Committee 1) Approved the preferred option for the future of the building at 24 Marine Place set out within this paper to enable the council to fulfil its statutory housing duties under S188 and S193 of the Housing Act 1996. 2) Approved a budget of £1,100,000 from the unallocated temporary and emergency accommodation budget to deliver the project, and to note that the actual sum required from this budget will be lower should we be successful in an application for grant funding from Homes England’s Single Homelessness Accommodation Programme (SHAP) for which Worthing Borough Council has been identified as a target authority. 3) Delegated authority to the Director for Housing and Communities to invite tenders for the construction work, and to enter into all necessary contracts to enable the project to progress through the construction phase to completion. Call-in The call-in deadline for the decisions will be 5pm on 23 June 2023.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
Report to Joint Strategic Sub-Committee (Worthing)
Summary
1. Purpose
1.1The report seeks approval for the re-development of the Council owned property at 24 Marine Place Worthing to provide temporary accommodation and for a budget to complete the development of the site.
1.2The report follows the publication of the Adur and Worthing Housing Strategy for 2020-2023, ‘Delivering Pathways to Affordable Homes’ document and subsequent Delivery Plans where plans for a housing development programme were set out.
1.3This report outlines the increasing demand for emergency and temporary accommodation (EA/TA) in Worthing, the Council’s commitment to owning its own stock of EA/TA, and reviews the options available to the Council for the future of the building with development of the site as temporary accommodation the preferred option both economically and in terms of meeting an established local need. 2. Recommendations
2.1To approve the preferred option for the future of the building at 24 Marine Place set out within this paper to enable the council to fulfil its statutory housing duties under S188 and S193 of the Housing Act 1996.
2.2To approve a budget of £1,100,000 from the unallocated temporary and emergency accommodation budget to deliver the project, and to note that the actual sum required from this budget will be lower should we be successful in an application for grant funding from Homes England’s Single Homelessness Accommodation Programme (SHAP) for which Worthing Borough Council has been identified as a target authority.
2.3To delegate authority to the Director for Housing and Communities to invite tenders for the construction work, and to enter into all necessary contracts to enable the project to progress through the construction phase to completion.
3. Context
3.1The building at 24 Marine Place and its adjacent small car parking area is owned by Worthing Borough Council and is situated in the South Street Conservation area in central Worthing. It was used as a youth drop in centre by WSCC for some years up until 2021 and most recently as a winter night shelter for the homeless. It is currently unoccupied.
3.2Redevelopment options for the building have been considered and the scope for its conversion and extension have been assessed and discussed with planning officers. In planning terms the current use is ‘sui generis’ or without designation so it has the potential to serve a number of uses. The current proposal is to convert the building to provide urgently needed temporary accommodation for homeless households and the policy background to support this is set out in the paragraphs below.
3.3Chapter 3 of the Housing Strategy outlines the local need for affordable housing, in the context of increasing prices and rents. Based on demographic projections, there is a need for 653 additional affordable dwellings (of all tenures) per annum across the region. 3.4 Priority 3 of the Housing Strategy demonstrates the Council’s commitment to the delivery of affordable housing, including a commitment to the delivery of 250 homes directly by Adur & Worthing Councils. This commitment is reiterated in ‘Delivering Pathways to Affordable Homes’ which was adopted in March 2021.
3.5Adur & Worthing’s Temporary Accommodation Strategy was adopted in 2017 and focuses on the placement and procurement of accommodation. There is recognition in the Housing Strategy that the Temporary Accommodation Strategy should be reviewed and updated with extra emphasis on developing our own accommodation for these purposes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Joint Strategic Sub-Committee (Worthing) at Adur & Worthing and we tell you when its next papers are published, before the meeting rather than after it.
CIL Neighbourhood Fund 2023 into 2024Decision 1. That the scheme continue with the same programme and governance structure used in 2023 and invite a parti...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.