Decision 1) That the report and projected outturn position for Worthing Borough Council against the approved revenue budgets and proposed use of reserves (Appendix 2b) be noted. 2) That the report and projected outturn position for Adur District Council against the approved revenue budgets and proposed use of reserves (Appendix 3b) be noted. Call In The call-in deadline for the decision will be 5.00pm on 19 December 2023
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1This report updates the Joint Strategic Committees with the latest expenditure and income projections for both Adur District Council and Worthing Borough Council for the current financial year 2023/24, compared to the Revenue Budget approved by both Councils in February. Whilst the 'spend to date' will be the position as at the 30th June 2023, the forecast outturn position will reflect the latest information available to ensure an up-to-date forecast is presented.
The current outturn projection for the 2023/24 financial year for the Worthing Borough Council General Fund is a net overspend after reserve transfers of £1.541m and for Adur District Council General Fund is a net underspend after reserve transfers of £33k. A breakdown is set out in section 4.4 of the report.
This position has been achieved as a result of a very significant in-year spend controls and savings process delivering £1.1m in forecast savings, largely counteracted by significant emerging new pressures.
1.2The following appendices have been attached to this report:
(i) Appendix 1 Briefing Note on Service Performance
(ii) Appendix 2 (a) Worthing Summary (b) Worthing Use of Earmarked Reserves iii) Appendix 3 (a) Adur Summary (b) Adur Use of Earmarked Reserves (iii) Appendix 4 (a) HRA Summary (b) HRA Major variances (c) HRA Briefing note (iv) Appendix 5 Table of Variations over £20,000
Recommendations
2.1The Joint Strategic Committee is asked to note the report and projected outturn position for Worthing Borough Council against the approved revenue budgets and proposed use of reserves (Appendix 2b).
2.2The Joint Strategic Committee is asked to note the report and projected outturn position for Adur District Council against the approved revenue budgets and proposed use of reserves (Appendix 3b).
3.0Context
3.1The Joint Strategic Committee last considered the 5-year forecast for 2023/24 to 2027/28 on 11th July 2023.
3.2The report set out the context of local government finance and the continuing uncertainty for councils across the country, with a lack of a multi-year settlement from central government. This is expected to remain the case until at least after the national general election in late 2024 / early 2025.
3.3The report also highlighted the importance of careful financial management in-year due to downward pressures on the councils’ commercial income post covid and in relation to the cost of living and broader inflationary effects such as the increased cost of goods and services. Moreover, increasing demands for emergency and temporary accommodation would continue to put significant pressure on budgets.
4.0Issues for consideration - Revenue 2023/24 Forecast
4.1As part of the 2023/24 budget the Councils committed to savings of £1.333m for Adur District Council and £3.203m for Worthing Borough Council to produce a balanced budget and to address the reduction in Government support. Delivery against these targets has been very successful, although there have been emerging additional pressures in-year.
4.2Further details are set out at 4.13 below, but a key uncertainty for the 23/24 budget has been the national pay award, which has only recently been agreed. This averages out at 5.8% which is higher than the assumed 4.5% built into the 2023/24 budget.
4.3Given the ongoing uncertainty around inflation, increased demand on services and energy resources and pricing, it is difficult to have certainty on the estimates and assumptions, however the current projections indicate forecast year end overspends against budgets of £1.541k in Worthing and an underspend of £33k in Adur. This is a positive position given the significant additional pressures that emerged in the first part of the year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.