Decision 1. That the progress made on projects and recommendations since the publication of the Carbon Neutral Plan be noted 2. That Carbon Management Plan be approved and adopted it be published on the councils' website Call In: The call-in deadline for the decision will be 5.00pm on 20 February 2024
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
FEBRUARY 2024 Background Following the joint declaration of a Climate Emergency in 2019, Adur & Worthing Councils published their Carbon Neutral Plan: Working towards the 2030 target. This was a science- and evidence-based Plan that identified key actions and intervention measures required to set the councils on the path to net zero carbon emissions.
The Carbon Neutral Plan aligned to the Councils' previous vision Platforms for our Places. This update The Carbon Management Plan now supports Our Plan, specifically the Thriving Environment ambition, which lists as a mission: Action now achieves a fair transition to Net Zero Carbon by 2045.
Whilst the councils' emissions only make up a fraction of one percent of the emissions from the area as a whole, achieving the Carbon Neutral target by 2030, the councils will be a model for all residents, organisations and businesses in Adur & Worthing, enabling us to lead the area towards net zero by 2045 through learning and shared infrastructure.
This refresh of the Carbon Neutral Plan comes four years after the previous plan was adopted and three years following the appointment of the carbon reduction team, which has, in partnership with colleagues from across both councils and external organisations, secured in excess of £10m of external funding and delivered a number of key interventions. Many of these are explained throughout the document.
Emissions Progress
As noted in the Carbon Neutral Plan, the scope for the councils' reductions was defined as being Scope 1 and 2 only. These are defined in Table 1, as follows:
Category Description Data used in this analysis
Scope 1 Direct emissions from sources owned or Metered gas data (or bills) controlled by the councils Litres of fuel purchased for council-owned vehicle fleet Pool car mileage
Scope 2 Indirect emissions from the generation of Metered electricity data (or energy (electricity) purchased by the bills) councils Table 1
As per the Carbon Neutral Plan, scope 3 emissions1 are not included within this analysis and will form a key part of the councils' work to deliver on its 2045 target.
1 Scope 3 emissions are indirect emissions that result from other activities that occur in the value chain of the reporting organisation, either upstream or downstream. Since the publication of the original plan, annual reports have been presented to the councils' Joint Strategic Committee that have set out year-on-year progress regarding the targets. These have also identified where further data (i.e. new metering and billing) has become available to the councils that allows for the direct comparison between the original baseline year (2019/20) and now (table 2).
tCOe2 2019/20 2022/23 % decrease
Electricity 856 638 25.5
Gas 979 821 16.2
Fleet and pool cars 1,197 1,092 8.8
Total 3,062 2,553 16.6% Table 2
This shows that the councils have reduced their emissions by over 500 tonnes, or 16.6% in the previous four years. Whilst this is good progress, it is evident that more needs to be done in order to ensure the 2030 target is reached.
This 2023 Carbon Management Plan updates the 2019 Carbon Neutral Plan by focusing on: ● Delivered projects and work ● Emissions reduction measures - only relying on offsetting where a reduction in emissions is infeasible, as defined by the UN ● Recommendations for further work to continue to deliver our progression to our 2030 target
Scope 1: Gas
The Carbon Neutral Plan identified the need to reduce heating demands and phase out natural gas usage across the councils' estate. This work has been split into two areas: gas for space heating and hot water; and gas consumption at the crematorium.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.