Refurbishment of Homefield Park Play Area

Agreed Committee 1 paper

Joint Strategic Committee agreed this item on Thursday 12 September 2024. Below is the council's own wording, with the papers it was decided on.

ItemJSC/30/24-25

Resolved

1) That the use of £220,000 from the capital programme for the redevelopment of Homefield Park play area be agreed; 2) That Worthing Borough Council’s intention to seek funding for the development of a SUD garden as Phase 2 of the project be noted, with an update expected back to this Committee in Q2 2025 to ensure progress; 3) That authority be delegated to the Assistant Director of Place & Economy, in consultation with the Cabinet Member for Environmental Services, the authority to approve and award all associated contracts for the final design and construction of the Homefield Park play area and SUDs Garden. Call In: The call-in deadline for decisions will be 5.00pm on 24 September 2024
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1. Purpose

1.1The purpose of this report is to outline to Members the plans to rejuvenate the play area at Homefield Park, Worthing - Phase 1.

1.2To outline proposals for a new SUDs (Sustainable Drainage Systems) garden in response to an area of parkland regularly at risk of water table ponding - Phase 2.

1.3To ensure Members are aware of the community consultation being undertaken to inform the design of the play area.

1.4To provide the necessary assurances for Members in relation to the use of approved capital PID expenditure for the play area rejuvenation. 2. Recommendations

2.1To agree to the use of £220,000 from the capital programme for the redevelopment of Homefield Park play area.

2.2To note Worthing Borough Council’s intention to seek funding for the development of a SUD garden as Phase 2 of the project, with an update expected back to this Committee in Q2 2025 to ensure progress.

2.3To delegate authority to the Assistant Director of Place & Economy, in consultation with the Cabinet Member for Environmental Services, the authority to approve and award all associated contracts for the final design and construction of the Homefield Park play area and SUDs Garden.

3. Context

3.1Homefield Park, built in 1880, was the first municipal park in Worthing. Known fondly as the ‘people's park’ , Homefield covered approximately 10 acres before being reconfigured to 14 acres in the late 19th century. Linking East Worthing residential areas to Worthing Hospital, Homefield Park is a short walk to Worthing town centre and neighbouring Beach House Park.

3.2As a leisure park Homefield Park offers multiple facilities, suitable for all ages. Activities include six newly refurbished tennis courts, a skateboard and BMX park, basketball, table tennis, children’s play area, teen shelter and outdoor gym. Popular with a wide demographic, Homefield park is regularly used by young families, teenagers, hospital staff/patients, town centre workers and dog walkers. Open space events such as fun fairs, festivals and live music are occasionally hosted on the grassed area in the centre of the park. Figure 2. Homefield Park

3.3A partial refurbishment of the play area took place in 2013 however, the majority of the equipment which still remains in Homefield park is significantly older than this, in poor state and well past its life expectancy. Capital works for the refurbishment of the play area was originally scheduled for 2022. These works were temporarily paused while the council reviewed its financial position as a result of external budget challenges and the Parks & Foreshore team experienced changes to its management structure.

3.4During the Victorian era Homefield Park featured an ornamental lake to the east side of the park ( figure 1), formed by damming the Teville Stream. In 1930 the pond was filled in, however, the low water table in this area continues to cause flooding to a section of the children's play area which currently occupies the site. Due to the natural ponding in this location trees, grass or ornamental planting are unsuitable as viable alternatives. Figure 1.

3.5The Friends of Homefield Park (FoHP) community volunteers are active supporters of the park. A long standing community group FoHP actively represents the interests of all park users, organising community events such as picnics, cleanups, a Jazz day and family fun days. An area of Homefield Park, The Haven, is a small community garden which is directly managed by FoHP and supported by the Parks team.

4. Issues for consideration

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Refurbishment of Homefield Park Play AreaAgenda 7.5 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
SC
Councillor Sophie CoxWorthing Member, present
RG
Councillor Rita GarnerWorthing Member, absent
ÖB
Councillor Ödül BozkurtWorthing Member, present
DF
Councillor Dom FordWorthing Member, present
JT
Councillor John TurleyWorthing Member, absent
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerChair, present
LC
Councillor Lee CowenVice-Chair, present
BA
Councillor Becky AllinsonAdur Member, present
JH
Councillor Jude HarveyAdur Member, present
SJ
Councillor Saffa JanAdur Member, present

All 13 on the meeting page

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open