1. Purpose
● This report follows on from the report to Joint Audit & Governance dated 11 March 2025 on the Buckingham Park Refurbishment Review (Item 11) which highlighted where governance processes were not followed. Members are referred to this report for background information only and the report is not reproduced here.
● The Joint Audit & Governance Committee recommended that the role of elected Member involvement in the Buckingham Road Multi-Storey Car Park (MSCP) process be referred to the Joint Overview & Scrutiny Committee.
2. Recommendations
● The Joint Overview and Scrutiny Committee are asked to note the contents of this report. 3. Context
3.1. On receipt of a report from the Assistant Director for Regenerative Development reporting on governance anomalies, the Joint Audit and Governance Committee raised a concern that there had been insufficient Member involvement in the Multi-Storey Car Park (MSCP) refurbishment project.
3.2. There is documented history of Cabinet Member involvement from project inception in 2018, to date. Member involvement has primarily occurred through formal committee structures, mostly the Joint Strategic Committee (JSC) and decisions made by relevant Executive Members, which are listed in the background documents for Members below.
3.3. However, as outlined in the 11 March 2025 JAGC report, our constitutional governance procedures were not followed and we have assessed the reason for this to be that two key members of staff left the Council towards the end of the project, and a more junior member of staff was not fully aware of the accurate budget position.
3.4. By way of background, the initial strategic direction for this project was provided in November 2018, when the Joint Strategic Committee authorised the retention and refurbishment of both High Street and Buckingham Road multi-storey car parks as part of a broader capital program report. This decision indicated a high-level strategic endorsement for the asset's future.
3.5. Financial decisions and project enhancements were also subject to cabinet member approval. In June 2020, the Joint Strategic Committee agreed to a budget virement of £800,000 from the High Street MSCP capital allocation to the Buckingham MSCP project budget. This was done to facilitate a larger refurbishment program and enable regenerative benefits and improvement options, driven by the impending demolition of the Grafton MSCP. This virement was unanimously agreed by the Joint Strategic Committee Committee. Later the same month, on 10 June 2020, the WBC Executive Member for Regeneration approved the appointment of Pick Everard of Perfect Circle to provide professional, multi-disciplinary construction consultancy services for the project, to the value of £246,100. The ADC Executive Member for Environment abstained from this decision as it was considered a Worthing matter. 3.6. In April 2022, the Executive Members for Regeneration (Worthing and Adur) were responsible for approving the award of the main refurbishment contract. The Worthing Executive Member for Regeneration approved acceptance of the submitted tender and the award of the contract to Makers Construction Limited for a sum within the authorised budget, to enable essential repairs and health and safety improvement works. Similar to the consultancy decision, the Adur Executive Member for Regeneration abstained as it was a Worthing issue.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Buckingham Road MSCP Scrutiny RequestReport | 226 KB | DownloadRead as text |
Follow Joint Overview & Scrutiny Committee at Adur & Worthing and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Jun 2026 | JOSC Work Programme ConfirmationAgreed to move the date of the July JOSC meeting from July 2 nd to July 9 th 2026. · Agreed to continue the Budget Sc... | Agreed | Open |
| 5 Mar 2026 | Annual feedback report from meetings of the West Sussex Health & Adult Social Care Scrutiny Committee (HASC)The Joint Overview and Scrutiny Committee noted the report | Noted | Open |
| 5 Mar 2026 | JOSC Work Programme Setting 26/27The Joint Overview and Scrutiny Committee Noted the progress made in delivering the JOSC Work Programme for 2025/26; ... | Noted | Open |
| 27 Jan 2026 | Confirmation of MinutesThe minutes of the meeting of the 4th December 2025 were approved as a correct record and be signed by the Chairman | Approved | Open |
| 27 Jan 2026 | Budget update and scrutinyThe Joint Overview and Scrutiny Committee: Noted the work undertaken by the JOSC Budget Scrutiny Working Group and su... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.