AI summaryJoint Strategic Committee approves extra £1,112,967 for Albion Street housing scheme, bringing total cost to £16.5m. 49 flats for social and affordable rent are nearing completion after original contractor went bust.
Written from the decision and the officer reportPDF Pro
OutcomeNotedVirement of £1,112,967 to finish Albion Street new build
Money£1,112,967 virement, total £16,500,000Funded from HRA Capital Asset Improvements budget
What happens nextNot stated
Who it affects49 flats, 32 social and 17 affordable rentedHoused by Adur Homes for people on housing register
What was decided
Members noted the cost increase but accepted the scheme still meets its financial targets. Report P5
A virement of £1,112,967 from the HRA Capital Asset Improvements budget was approved to finish the project. Report P5, P38
Authority was delegated to the Director for Housing and Communities to sign contracts and legal documents needed to complete construction. Report P6
Why
The original contractor, Westridge Construction, went insolvent in September 2023 and a completion contract was awarded to J. Cheesmur and Sons Limited. Report P9
Extra costs have arisen from cladding and water ingress repairs, defective work, professional fees, longer build time, and higher interest rates. Report P19, P21, P29
The Building Safety Act 2022 introduced new digital record requirements, adding further compliance work for the building, classed as a Relevant Building. Report P11, P15
What happens next
Cheesmur and Sons Limited will continue construction to practical completion, with Adur Homes Lettings Team preparing to allocate the flats. Report P10, P14
Officers will work with the contractor and design team to provide the digital records needed under the Building Safety Act. Report P11
The remaining overspend of £1,112,967 will be vired from the 2025/26 HRA Capital Budget, which falls from £17,662,100 to £16,549,133. Report P39, P40, P41
The money
£1,112,967 Additional budget virement to complete Albion Street Report P5, P38
£15,387,033 Approved budget to date Report P27
£14,961,181 Costs to date Report P27
£1,538,819 Other costs to date to achieve completion Report P27
£16,500,000 Total costs to complete Report P27
£1.776m Virement approved by JSSC in February 2024 Report P13, P17
£998k Expected insurer claim under insolvency bond Report P13, P17
£465,456 Additional capital budget from Q1 Capital Monitoring Report Report P37
£17,662,100 2025/26 HRA Capital Budget before approval Report P39
£16,549,133 2025/26 HRA Capital Budget after approval Report P41
£1.4m Forecast positive cash return over 40-year life Report P31
(£9,076,418) Net Present Value, negative return over 40 years Report P31, P32
(145,620) Year 1 net cost to Housing Revenue Account Report P34
£13.8m Assumed disposal value at end of 40-year lifespan Report P31
Options considered
Chosen: Vire £1,112,967 from HRA Capital Asset Improvements to complete the project. Scheme cannot be left uncompleted and the additional spend keeps the project viable, with most of the vired budget reimbursable through the performance bond. Report P5, P38, P48
Rejected: Leave the project dormant. Not a viable option; the building must be completed. Report P48
Implications
Financial: Total project cost rises to £16,500,000, with a negative Net Present Value of £9,076,418 over 40 years, though the scheme is forecast to return £1.4m in cash over that period. Report P27, P31, P32
Financial: The HRA will bear a net annual cost until year 26 of the scheme. Report P31, P35
Legal: The Council relies on Section 111 Local Government Act 1972, Section 3 Local Government Act 1999, and Section 1 Local Government (Contracts) Act 1997 to enter the contracts. Report P43, P44, P45
Legal: The building is being brought into compliance with the Building Safety Act 2022 as a Relevant Building, including a Golden Thread digital record. Report P11, P15
Equalities: Equality issues were considered and no impact was identified. Report 2.2
Climate: Environmental issues were considered and no impact was identified. Report P54
Risk: Rising interest rates during the extended build and rent being capped at Local Housing Allowance rates limit cost recovery. Report P21, P30
Who and where
People on Adur's housing register, who will be allocated the 49 flats once complete Report P14, 2.1
Adur Homes tenants and the Housing Revenue Account, which will bear net annual costs until year 26 Report P31, P35
J. Cheesmur and Sons Limited, the completion contractor Report P9
Adur District Council as landlord of the completed building Report P15
Timeline
February 2020: Original budget of £12.191m approved at JSC Report P26, P46
September 2023: Original contractor Westridge Construction became insolvent Report P9
February 2024: JSSC approved virement of £1.776m and procurement of completion contract Report P2, P13, P17
July 2024: JSC received a further financial update Report P8, P46
9 October 2025: JSC approved the additional £1,112,967 virement Report P5
21 October 2025, 5.00pm: Call-in deadline for the decision
Year 26 of the scheme: First year the scheme is forecast to deliver a net return to the HRA Report P31, P35
End of 40-year lifespan: Assumed disposal of the building at £13.8m Report P31
Plain English for the jargon
Virement: Moving budget from one approved heading to another within the same overall budget.
HRA: Housing Revenue Account, the ringfenced account councils use for income and spending on council housing.
Golden Thread: A mandatory digital information system required under the Building Safety Act 2022 for higher-risk buildings.
Relevant Building: A building defined under the Building Safety Act 2022 as needing additional safety and information requirements.
Net Present Value (NPV): A measure of an investment's value after adjusting future cash flows for the time value of money.
LHA rate: Local Housing Allowance rate, the cap on housing-related benefits used here to set maximum rents and service charges.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/58/25-26
Resolved
That the issues that have arisen and the anticipated net increase in costs to complete the project be noted, and that the impact on scheme viability is that it still achieves the necessary financial targets. 2. That the virement of an additional budget of £1,112,967 be approved to enable the project at Albion Street to be completed. This virement was from existing budgets for Housing Revenue Account (HRA) Capital Asset Improvements. 3. That authority be delegated to the Director for Housing and Communities to enter into all necessary contracts and associated legal documentation to enable the project to progress through the remaining construction phase to completion. Call In: The call-in deadline for decisions will be 5.00pm on 21 October 2025
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1. Purpose 1.1. The report sets out the latest position on the Albion Street new build project and seeks approval of additional funds to support its delivery.
1.2. Joint Strategic Sub-Committee (Adur) Members were previously updated in February 2024 of the background to this project and the works proposed to complete the project following the original contractors insolvency in August 2023. A completion contract is underway.
1.3. Since this report a number of issues have arisen which now require additional costs to complete the project. This report sets out these issues, the anticipated completion date and the financial proposal and implications for the Council.
2. Recommendations
2.1. To note the issues that have arisen and the anticipated net increase in costs to complete the project, and that the impact on scheme viability is that it still achieves the necessary financial targets. 2.2. To approve the virement of an additional budget of £1,112,967 to enable the project at Albion Street to be completed. This virement is from existing budgets for Housing Revenue Account (HRA) Capital Asset Improvements.
2.3. To delegate authority to the Director for Housing and Communities to enter into all necessary contracts and associated legal documentation to enable the project to progress through the remaining construction phase to completion
3. Context
3.1. The background to this development of 49 flats (broken down as 32 social rented homes and 17 affordable rented homes) for affordable rented housing was presented to Joint Strategic Sub-Committee Members in February 2024 with a further financial update provided to Joint Strategic Committee in July 2024, these previous report has been added as background papers.
3.2. The original development was undertaken by Westridge Construction. They became insolvent in September 2023 and a completion contract procured with an initial assessment of costs to complete the project being presented to Members. The compilation contract was awarded to J. Cheesmur & Sons LTD and they have been working through the project.
3.3. Since that date, Cheesmur, undertaking the work as part of the completion contract has been working through the challenges identified and is nearing practical completion for the properties to be handed over to Adur Homes for occupation of local residents in housing need.
3.4. Since development commenced the Building Safety Act has been introduced. Buildings of a certain height are defined as either Relevant Buildings or High Risk Buildings. Additional requirements include a Golden Thread which is a mandatory digital, secure, and accessible information management system required for all Higher-Risk Buildings (HRBs) to ensure ongoing safety. There are nuances in how it's implemented for high-risk versus relevant buildings. While the fundamental requirement is the same, maintaining a comprehensive digital record throughout a building's lifecycle, the key difference is the scope and intensity of the requirements for high-risk buildings, which are more strictly defined by height or storeys and have specific design and management responsibilities mandated by the Building Safety Act 2022. The challenge for this project is that it did not start out as a ‘golden thread’ project and therefore some of the information required for the digital records may not be available. Council officers are therefore working through this with the current contractor and their design team at present.
3.5. Alongside this, professional fees for design works, planning requirements, and consultants have all continued and have been a necessity.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.