Adur District Council / Worthing Borough Council
Joint Audit and Governance Committee, Tuesday 16 June 2026 at 6.30pm

2025/26 Internal Audit Annual Report(s) and Opinion

Decided Finance 1 paper

AI summaryJoint committee considers 2025/26 internal audit report giving Adur and Worthing Councils a second consecutive 'Limited' opinion on governance, risk management and control.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedLimited assurance opinion on framework of governance, risk management and control
MoneyNot stated
What happens nextIndividual annual reports to each CouncilTo inform each Council's annual Governance Statement
Who it affectsAdur District and Worthing Borough CouncilsGovernance, risk management and control arrangements

What was decided

The Joint Audit and Governance Committee considered the 2025/26 Internal Audit Annual Report and Opinion prepared by Forvis Mazars LLP, covering the year ending 31 March 2026. Report P10

The auditors gave an overall opinion that the framework of governance, risk management and control is 'Limited' in its overall adequacy and effectiveness, the same level as in 2024/25. Report P11, P51

Why

Eight of twelve assurance reviews received Limited opinions, including Leisure Contract Health & Safety, Equalities Act Compliance, Corporate Fire Safety, Procurement / Contract Management, IT Third Party Risk Management, Capital Programme, Landlord Health & Safety, and IT Network Security and Resilience. Report P11, P14, P15, P16, P18, P19, P20, P24, P26

Four reviews (Commercial Fire Safety, Commercially Leased Buildings, Out of Hours Service, and Risk Management) received Moderate assurance, and High priority recommendations were raised in six reviews. Report P11, P17, P21, P22, P28

Common weaknesses across reviews related to lack of formalisation of governance and accountability, inconsistent performance monitoring without defined KPIs, and gaps in documenting decisions and controls, often linked to capacity constraints. Report P38, P39, P40

What happens next

75 recommendations (9 High, 39 Medium, 16 Low and 11 Advisory) have been raised, with all accepted by management, and implementation is tracked through a live actions tracker reported to JAGC. Report P11, P36, P38

Three reviews (Building Control, Anti-Social Behaviour, and Data Privacy/Information Governance) were deferred to the 2026/27 Plan, and three (ESG and Sustainability, Planning Policy, General Compliance) were cancelled at the July 2025 JAGC. Report P27, P29, P34, P35

Follow-up work showed 85% of recommendations implemented or superseded, up from 37% the previous year, with the February 2026 review reaching 92% verification. Report P11, P46, P48, P49

Options considered

  • Chosen: Limited annual opinion (2025/26). Eight of twelve assurance reviews received Limited opinions and six reviews had High priority recommendations Report P11, P51
  • Chosen: Cancelled 2025/26 reviews: ESG and Sustainability, Planning Policy, General Compliance. Approved for cancellation at July 2025 JAGC; some days repurposed to support other reviews and follow-up Report P10, P34, P35
  • Chosen: Deferred 2025/26 reviews: Building Control, Anti-Social Behaviour, Data Privacy/Information Governance. Moved to the 2026/27 Plan Report P27, P29, P35

Implications

  • Risk: Significant weaknesses remain in governance, risk management and control arrangements, with High priority recommendations in areas including fire safety, procurement, IT security and equalities compliance. Report P11, P14, P15, P16, P18, P19, P26
  • Other: Auditors identified capacity and resourcing constraints as a recurring factor limiting documentation and evidence of controls, and were unable to obtain complete or reliable data sets in several reviews. Report P38, P40
  • Staffing: Resource constraints within the Councils were observed to affect timely maintenance of registers, monitoring records and system updates, particularly in fire safety, leased buildings and key financial systems. Report P40
  • Governance: Recommendation implementation rate rose to 85% from 37% the prior year, with all recommendations accepted by management, and clear ownership assigned. Report P11, P38, P46

Who and where

  • Adur District Council and Worthing Borough Council (joint arrangements) Report P1, P10
  • Members and officers of the Joint Audit and Governance Committee Report P10, P11
  • The Director of Finance and finance staff Report P10, P40
  • Service areas covered by the 14 reviews, including Leisure, Equalities, Fire Safety, Procurement, IT, Capital Programme, Housing/Adur Homes and Out of Hours services Report P14, P15, P16, P17, P18, P19, P20, P22, P24, P26

Timeline

  • 2025/26: Internal audit year covered by the report, ending 31 March 2026 Report P10
  • December 2024: External Quality Assessment confirmed Forvis Mazars 'Generally Conform' with professional standards Report P40
  • May 2025: Original Internal Audit Plan approved by JAGC Report P40
  • May 2025, September 2025, February 2026: Three follow-up reviews carried out to verify implementation of previous recommendations Report P42, P49
  • July 2025: JAGC approved cancellation of three reviews (ESG and Sustainability, Planning Policy, General Compliance) Report P34, P35
  • 04 June 2026: Date of the combined draft Internal Audit Annual Report Report P3
  • 16 June 2026: Date the report was considered by the Joint Audit and Governance Committee

Plain English for the jargon

  • Limited assurance: Significant weaknesses in the framework of governance, risk management and control such that it could be or could become inadequate and ineffective.
  • Moderate assurance: Some improvements are required to enhance the adequacy and effectiveness of the framework of governance, risk management and control.
  • JAGC: Joint Audit and Governance Committee of Adur District Council and Worthing Borough Council.
  • GIAS: Global Internal Audit Standards, issued by the Institute of Internal Auditors (effective January 2025).
  • Follow Up review: Internal audit work that checks whether previously accepted recommendations have been implemented, rather than raising new recommendations.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJAGC/9/26-27

Resolved

The Joint Audit and Governance Committee
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Audit and Governance Committee

Adur & Worthing Councils

Internal Audit Annual Report 2025/26 – Combined Draft

Prepared by: Forvis Mazars LLP Date: 04 June 2026 Contents 01 Introduction

02 Annual Internal Audit Opinion

03 Internal Audit Work Undertaken in 2025/26

04 Cultural and Behavioural Factors

05 Cross-Organisational Themes / Insights

06 Performance of Internal Audit

Disclaimer This report (“Report”) was prepared by Forvis Mazars LLP at the request of Adur District Council and Worthing Borough Council (the Councils) and terms for the preparation and scope of the Report have been agreed with them. The matters raised in this Report are only those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the information provided in this Report is as accurate as possible, Internal Audit have only been able to base findings on the information and documentation provided and Appendices consequently no complete guarantee can be given that this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that may be required. A1 Implementation of Recommendations The Report was prepared solely for the use and benefit of the Councils and to the fullest extent permitted by law Forvis Mazars LLP accepts no responsibility and disclaims all liability to any third party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any extract, reinterpretation, amendment A2 Year-on-Year Benchmarking and/or modification. Accordingly, any reliance placed on the Report, its contents, conclusions, any extract, reinterpretation, amendment and/or modification by any third party is entirely at their own risk. Please refer to the A3 Definitions of Assurance Statement of Responsibility on Page 11 of this report for further information about responsibilities, limitations and confidentiality. Contacts and Statement of Responsibility

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Internal Audit Annual Report(s) and OpinionReport 751 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 18 attended
SF
Simon FillerOfficer, expected
DS
Councillor Debs StainforthChair, present
KD
Councillor Kate DavisVice-Chair, present
CF
Councillor Carolyn FuhrmannAdur Member, present
DD
Councillor David DevoyAdur Member, absent
CA
Councillor Carson AlburyAdur Member, absent
JD
Councillor Jim DoubtfireAdur Member, present
RG
Councillor Rhys GrinsteadAdur Member, present
NS
Councillor Nigel SweetAdur Member, present
DA
David AllumCo-Optee, present
RW
Councillor Rosey WhorlowWorthing Member, absent
JR
Councillor Jon RoserWorthing Member, present

All 18 on the meeting page

On this subject at Adur & Worthing

Search all
  1. 2025/26 Internal Audit Annual Report(s) and OpinionThis decision
  2. Internal Audit Progress ReportNoted
  3. Internal Audit Progress ReportNoted
  4. Internal Audit Progress ReportNoted
  5. Internal Audit Progress ReportNoted
  6. Internal Audit Progress ReportNoted

More from Adur & Worthing Joint Audit and Governance Committee

All decisions
MeetingDecisionOutcome
22 Sep 2026 Risks & Opportunities Update ReportAgreed to receive a further progress report in March 2027. Agreed Open
16 Jun 2026 25/26 Audit Planning ReportThe Joint Audit and Governance Committee noted the report Noted Open
16 Jun 2026 Internal Audit Progress ReportThe Joint Audit and Governance Committee noted and considered the contents of the report Noted Open
16 Jun 2026 Audit enquiries to those Charged with GovernanceThe Joint Audit and Governance Committee considered and agreed to the proposed responses to the external auditor’s le... Agreed Open
16 Jun 2026 Code of Corporate Governance UpdateThe Joint Audit and Governance Committee Noted that the guidance to the Code of Corporate Governance was approved by ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies