Resolved
Decision Agreed to note:- 1. The establishment of the Central Heating Initiative. 2. The arrangements emerging for its operation within Argyll & Bute (Ref: Report by Director of Housing & Social Work dated 8 October 2001, submitted).
Strategic Policy Committee agreed this item on Thursday 18 October 2001. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Agreed to note:- 1. The establishment of the Central Heating Initiative. 2. The arrangements emerging for its operation within Argyll & Bute (Ref: Report by Director of Housing & Social Work dated 8 October 2001, submitted).
a 2.1 Members are asked to note:
a) the establishment of the Central Heating Initiative.
b) the arrangements that are emerging for its operation within Argyll & Bute.
3. DETAIL
3.1Background: The Scottish Executive announced its proposals for the establishment of a Central Heating Initiative on the 1" April 2001. This is due to run for four years and is designed to enable the provision of central heating in all homes that lack it. The Initiative also contains measures to help eradicate fuel poverty.
C:\windows\Temporary Internet Files\OLK82F4\09CRC~alH h g 4 9 4 . d o c 32
3.2Under the scheme, a grant of up to $2,500 will be payable to allow the provision of the undernoted package:
a central heating system, to cover at least the main living area, the hall, the bathroom, and the main bedroom(s)
insulation comprising, where practicable, cavity fill, loft, tank, and pipe insulation, hot water tank jackets and draft proofing
a cold alarm and carbon monoxide detector (where applicable) and a mains linked smoke detector
As a condition of this provision, householders must also receive advice on the use of the system, the efficient use of energy and budgeting, together with a check on their entitlement to state benefits.
3.3Audit Arrangements: The Scottish Executive intend to audit all 0 provision made under the Initiative by arranging for the conduct of entry and exit surveys which will record characteristics of individual properties before and &er the installation work takes place.
3.4As far as possible, householders are to be afforded choice. In this regard, Argyll & Bute Council has already highlighted the fact that solid fuel systems cost well over the &2,500threshold but the Scottish Executive reaction has been to say where such systems are installed, it will be for individual local authorities to pay the balance from their mainstream funding.
3.5Expected Outcomes: While the expected outcomes are similar, the arrangements for the delivery of the scheme differ between the local authority and private housing sectors. Members are asked to note the principal differences as detailed within the following sections, 0 3.6 Provision of Central Heating in Local Authority Housing: Earlier this year, in common with other local authorities, Argyll & Bute Council was asked to provide an estimate of the number of dwellings in their stock which lack central heating. Subsequently, the Scottish Executive defined central heating as:
a system which provides warmth to two or more rooms in dwelling through a series of connected radiators or ducts linked to a central boiler, or a series of electric storage heaters controlled from a central point.
3.7The Scottish Executive made clear that grant will not be paid to cover the cost of any systems installed for the first time prior to 2001. They have also excluded from consideration any dwellings scheduled for closure, demolition, or transfer within the next three years. Additionally, at this stage, dwellings served by ageing full and partial systems are also being excluded. 33
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
THE SCOTTISH EXECUTIVE CENTRAL HEATING INITIATIVEReport | 261 KB | DownloadRead as text |
Follow Strategic Policy Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2007 | Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... | Noted | Open |
| 19 Apr 2007 | North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... | Agreed | Open |
| 19 Apr 2007 | Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... | Noted | Open |
| 19 Apr 2007 | Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... | Agreed | Open |
| 19 Apr 2007 | Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.