Decision 1. Agreed the contents of the report, the draft submission and the decisions made by the Project Team. 2. Agreed that the bid be forwarded to the Scottish Executive. (Ref: Report by Head of Information Technology Infrastructure dated 16 November 2001, submitted and draft submission previously circulated to members only).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL STRATEGIC POLICY COMMITTEE INFORMATION TECHNOLOGY 29 November 2001
Digital Communities Competition - Project Update I,SUMMARY 1.I. The Scottish Executive recently announced the Digital Communities Competition where 2 disadvantaged Scottish communities of up to 2000 homes will be supplied with a PC,Printer, Software, Iyear’s non-metered lnternet access, and the development of a community portal web site designed to tackle issues arising as a result of social or geographic deprivation.
1.2.All Scottish Local Authorities have been asked to participate and complete an initial expression ofinterest by 30 November 2001. A shortlist of bids will then progress to the second, more detailed selection stage and the two winning bids (one from a rural and one from an urban authority) will be announced at the end of March 2002.
1.3The Management Team agreed at their meeting of 22 October to form a project team with the aim of compiling the strongest possible rural bid. The team has included representatives from many Council Departments and much detailed work has already been completed in researching and compiling our submission.
1.4.This paper aims to inform Members of the progress made so far. It should be noted that the tight timescales involved and the Council’s determination to submit a more than credible proposal, will result in the team continuing to develop the submission right up until the closing date.
2. RECOMMENDATION 2.1. Members are asked to note the contents of this report, the attached draft submission and note the following decisions made by the project team;
2.1I . The project team was asked to focus on a community most affected by geographic deprivation. The community selected includes 13 of the Council’s 26 inhabited islands referred to (for the purposes of this project) as the North Argyll Islands. They are; 46
2.1.2. The project will develop and enhance the “basic” provision of a standard PC, printer, and lnternet access by upgrading the specification to a multimedia PC with web-cam and by deploying advanced multimedia technologies designed to create a true, all encompassing, digita1 community.
2.1.3. If the bid proves successful, a number of senior partners, including the Council, will work together during the implementation phase of the project and wilt continue to help sustain the new community before the ultimate goal of a self-sustaining environment is achieved. This will require some financial assistance from the Council in years 2 and 3 of the project (2003/4,2004/5). The levels of expected assistance are not expected to exceed f100,OOO in each year. The Council will also support a European Funding proposal to help contribute to the ongoing costs associated with the project.
3. DETAIL 3.1.The Scottish Executive asked each Authority to complete a bid ternplate entitled “Digital Communities - Initial Expression of Interest”. Guidelines distributed with the template suggested we need only complete the first four sections and, if time allowed, provide further supporting information in the remaining seven sections. Argyll and Bute’s project team will complete all sections of the template.
3.2.The first meeting of the Project Team was attended by Rona Hamilton, the Executive’s Digital Communities Project Manager, and, in answer to our many questions, Rona clarified a number of additional issues:
The Executive will procure all hardware, internet services, support and initial training using the majority of the E 1.75million fund.
The specification of the hardware will be determined after analysing the bids received in the first round.
The Executive will engage a partner to carry out before, during and after evaluation of the impact of the bid.
Computer equipment will be provided to all households in the community where existing similar specified equipment does not already exist
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.