Item10
Resolved
Decision Agreed that:- 1. The recommendations contained within the Campbeltown Community Project and Burnet Project Reports be noted. 2. The Consultants for the Campbeltown Community Project be contracted to proceed with the project and that a further report be submitted at the end of Stage E of the process. The cost of taking the project to Stage E in professional fees is £191,800. 3. That the Policy Development Group established in terms of item 9 of this minute have included within their remit to progress the funding package for the programme and to report back to the Strategic Policy Committee with recommendations. 4. A funding application be re-submitted to Historic Scotland in respect of the Burnet Project. (Ref: Report by Director of Development & Environment Services dated 2 May 2002 and Extracts and Reports considered by the Mid Argyll, Kintyre & Islay Area Committee on Campbeltown Community Project and Burnet Project, submitted).
Word for word from the decision Argyll and Bute published for this meeting.