CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Policy Development Group, Monday 20 May 2002 at 3.00pm

KPMG REPORT ON REVIEW OF LEISURE SERVICES

Agreed Committee 1 paper

Policy Development Group agreed this item on Monday 20 May 2002. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision 1. In relation to the short term actions recommended in the Director’s report the Group agreed:- Helensburgh Swimming Pool Continue consideration pending outcome of development proposals for the site. Victoria Hall, Helensburgh Continue and noted that Council had made provision for roof repairs. Rothesay leisure Pool Noted this required an assessment of life-cycle costs. Pavilion, Rothesay Noted that a building survey would be completed in July and would be brought to this Group. Corran Halls, Oban Noted the ongoing progress for phase 2. Campbeltown Community Project As in item 3 of this minute. Riverside Centre, Dunoon Noted this required assessment of life-cycle costs. Queen’s Hall, Dunoon Noted that the local group established by the Area Committee would report back to this Group. Bowmore Hall and Ramsay Memorial Hall, Islay That a report be presented to the next meeting of this Groupwith recommended options including consideration of the use of the High School. Victoria Hall, Campbeltown Noted that they would require to be declared surplus once Community Project is complete Town Hall, Campbeltown That the original report on the Town Hall prepared at the time the Common Good Fund took some responsibility for the hall be brought to the next meeting of this Group. 2. The medium term actions and the strategic proposals recommended in the Director’s report were continued for consideration at a later date.. (Reference: Reports by the Director of Development and Environment Services 18 April 2002 and KPMG Report on review of Leisure Services).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy Development Group

Recommendations

2.1That the recommendations contained with the Campbeltown Community Project and Burnet Project Reports be approved. 2.2 That the consultants for the Campbcltown Community Project be contracted to proceed with the project and that a further report be submitted at the end of Stage E of the process. The cost of taking the project to stage E in professional fees is E1 91,800 (see appendix). 2.3 That a MembedOfficer Working Group be established in order to progress the hnding package for the programme and that this group meets at an early date with a view to reporting back to the Council with recommendations.

Background

As outlined, both projects have completed feasibility stage and the Area Committee has accepted the recommendations.

In order to meet the project timescales, the most important of which is to meet the fimding agencies deadlines, applications must be prepared over the summer. These cannot be submitted until planing permission has been granted and land ownership confirmed. The recommended site for the cornmiinity project is in Council ownership. This gives a significant boost to the financial position of Council and gives credibility to the grant applications. The Burnet project cannot be started in hill prior to the completion of the community project in Spring/Summer 2004. This 2-year period is the estimated timescale for obtaining funding from Heritage Lottery for the Bumet project. Approval for the architects to proceed at an early date is therefore essential to the implementation of the project.

4. DETAIL

4.1PROPOSED CAPITAL FUNDING ARRANGEMENTS

Funding Agencies (Capital) It is estimated that the capital cost of the project will be in the order of &5,750,000,including fees and internal fittings. The professional fee element of the project is attached. 4.1.1 Objective One Transitional Programme It is unlikely that funding would be forthcoming for a single element of the project. As the project involves a number of different but related elements of a community %825,000 nature it is regarded as a good example of joined up working and partnership activity which would be likely to receive an estimatedl5% of project costs at around 5825,000. Applications require to have ownership and planning permission approvals in which case an application should be submitted in the very near future. Ongoing discussions with the programme Convenor and Director have indicated that, in principle, the figure indicated would be a reasonable expectation assuming other funding is confirmed. This figure is based on a 22million contribution from the Council. 4.1.2 Sportscotland Following discussions with Sportscotland, the figure forthcoming is likely to be &700,000based on a two-stage application. However, there is also the opportunity to $700,000 apply for additional funding in relation to specific elements of the project e.g. playing fields (which are not included in the current costing estimates). This is under discussion. Given the timescales involved the stage one application will require to be submitted immediately. Ongoing discussions are taking place with senior officials from Sportscotland. This figure is based on a 22million contribution from the Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
KPMG REPORT ON REVIEW OF LEISURE SERVICESReport 900 KB DownloadRead as text

At this meeting

Whole meeting
4BURNET PROJECTOn the agenda
5KPMG REPORT ON REVIEW OF LEISURE SERVICESThis decision

Who was there

0 of 16 attended
AM
Archie MortonOfficer, expected
AM
Councillor Allan MacaskillMember, expected
RB
Councillor Robin BanksMember, expected
SM
Stewart McGregorOfficer, expected
GF
Councillor George FreemanMember, expected
GH
George HarperOfficer, expected
DK
Councillor Donald KellyMember, expected
EM
Councillor Ellen MortonMember, expected
EM
Elma MunroOfficer, expected
KM
Kate MurrayOfficer, expected
CR
Charles ReppkeOfficer, expected
LS
Councillor Len ScoullarMember, expected

All 16 on the meeting page

More from Argyll and Bute Policy Development Group

All decisions
MeetingDecisionOutcome
20 Feb 2007 Political management arrangementsDecision That the Director of Corporate Services finalise the draft report to reflect the discussion at the meeting a... Decided Open
9 Feb 2007 Consider information required to undertake remitDecision That the Policy Development Group recommend to the Strategic Policy Committee that they note: 1. the positiv... Decided Open
31 Jan 2007 Councillor remunerationDecision The Group noted the contents of the report and the representations made on behalf of the Council. (Ref: Repo... Noted Open
31 Jan 2007 Councillors' allowances and expenses regulations 2007Decision 1. The Group noted the report and the representations that had been made on behalf of the Council, including... Noted Open
31 Jan 2007 The scottish parliament: an awareness seminar for new councillorsDecision Agreed that the Director of Corporate Services accept the offer from The Scottish Parliament and that this b... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies