Decision 1. Agreed that the projects indicated in appendix 1 of the submitted report to a value of £598,124 are managed centrally by staff in Amenity Services with work delivered at the Areas. 2. That the residual funding from the European Transition Programme, with an indicative value of £355,328 is allocated by Area Committees over the next three years. 3. To note that funding beyond year 3 of the Programme is likely to be dependent on the success of achieving funding from the Executive’s Strategic Waste Fund. (Councillor Freeman, having moved an amendment which failed to find a seconder required his dissent from the foregoing decision to be recorded) (Ref: Reports by Director of Development & Environment Services dated 18 April 2002 and 30 May 2002 and Extract Minute of the Council of 2 May 2002, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The Council at its last full meeting on 2 May 2002 remitted consideration of the non-committed European Transition Funding to the Strategic Policy Committee with full powers to determine the utilisation of this funding.
1.2This report suggests the allocation of the non-committed funding in a way which will continue its spend in the areas, but deal with strategic elements centrally.
Recommendations
2.1That the projects indicated in Appendix 1 of this report to a value of £598,124 are managed centrally by staff in Amenity Services, with work delivered at the areas.
2.2That the residual funding from the European Transition Programme, with an indicative value of £355,328 is allocated by Area Committees over the next three years.
2.3That Members note funding beyond year 3 of the Programme is likely to be dependent on the success of achieving funding from the Executive's Strategic Waste Fund.
3. DETAIL
3.1In allocating the residual funding from the European Transition Programme, it has been recognised that some of the projects being delivered at individual areas will be particularly relevant to ensuring the strategic needs of the Waste Management Service are realised. The provision of kerbside recycling services throughout Argyll and Bute would be seen as the major priority in this and will be managed centrally by the Kilmory staff, with the service being delivered at area level. Appendix 1 to this report outlines the various elements of the service being introduced or extended throughout Argyll and Bute.
3.1.2 The previous plans for allocation of this funding indicated a potential to put in place litter bin purchase at each area. Given that there will be economies of scale in purchase and distribution if this is done centrally, it makes sense to allocate this funding to the Waste Management Staff at Kilmory.
3.1.3 Taking account of the potential spend for kerbside collection and litter bins outlined in Appendix 1, the residual budget available for area allocation is £346,328. Appendix 2 of this report lists potential ways for each Area Committee to spend a quarter of this over the next three years. It is intended that these lists form the basis of reports for Members’ consideration at their Area Committee Cycle in June.
3.1.4 In previous consideration of the European Transition Funding, concern has been expressed by the Director of Finance at the uncertainty of future budgetary settlements for the Council in overall terms. As has been previously indicated the long term future of many of the initiatives brought forward from this funding will be dependent on a successful application to The Scottish Executive's Strategic Waste Fund. Given the current timetable for submission of applications to the Strategic Waste Fund - by late Summer 2003 – it should be apparent well within the three year timescale of the Transition Programme Funding whether or not continuity of some of these schemes will be feasible. There can, therefore, be planning for continuation, or retrenchment, dependent on the outcome of any application, which is submitted within the next 12 months.
5. IMPLICATIONS
Policy: Builds the application of the European Transition Funding into the Service Planning and Budgeting Process.
Financial: No change from previous reports - all of the projects indicated in this report are not yet budgeted within Amenity Services. Due to the later phasing of some of the work, it may be that complete spend, either at the centre or areas varies from that shown in the Appendices. This might involve some of the spend being delayed until 2005/06 or spending within the three year programme being slightly different to that indicated. This can be controlled by the way in which the funding is drawn down and held in a separate account which can be carried forward between financial years.
Personnel: None
Equal Opportunity: None
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.