Strategic Policy Committee (Education) noted this item on Thursday 15 August 2002. Below is the council's own wording, with the papers it was decided on.
Decision 1. Noted the content of the report and agreed that the project team and advisers produce a strategic options paper for the schools estate together with a revision of the Outline Business Case as soon as possible and report back to the Strategic Policy Committee. 2. That the project team be requested to raise with the Scottish Executive, the Council’s and its co-sponsor’s, concern to ensure an early indication of Minister’s backing for the project. (Ref: Report by Director of Education dated July 2002, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This paper provides detail of the award announcement made by the Executive. It notes that different interpretations have been used regarding capital expenditure costs. Clarification has been received from the Executive on this issue together with an indicative offer of revenue support. The paper notes that whilst a lower level of support has been made available this still represents a significant capital sum available for investment in the schools estate. The OBC (Outline Business Case) now requires to be reviewed in the light of this offer.
Recommendations
2.1The Strategic Policy Committee is asked to note the content of this paper and agree that the project team and advisers produce a strategic options paper for the schools estate together with a revision of the OBC as soon as possible.
3. DETAIL
3.1Argyll and Bute Council and their advisers used the term “capital expenditure” to refer to the amount of money necessary for the up-front rebuild and refurbishment costs in schools. The Scottish Executive (SE) used the term to refer to the whole- life capital costs for the project. Whilst the SE interpretation included the rebuild and refurbishment capital costs, it included also:
• the cost of capitalised interest during construction; and, • the cost of capitalisation of 50% of future lifecycle maintenance.
3.2Throughout the OBC, and in public, the figure used to describe the level of this Council’s bid to the Executive was £90.11 million. At the announcement of the awards it was stated that Argyll and Bute Council has asked for £151 million and had been allocated £80 million. The £151 million referred to the Executive’s interpretation i.e. whole life project capital expenditure. Considerable confusion ensued as clarification was sought on the detail of this announcement.
3.3The Scottish Executive have now confirmed that the level of annual revenue support they are prepared to provide is capped at £5.73 million per annum over 30
MG/KH/i/Committee/SPC/15aug02/SEEDAnnouncement: Clarification of Award 1 years. The original bid in the OBC proposed a level of support of £8.86 million. Although reduced, this level of support will realise a significant capital investment sufficient to make an immediate and lasting impact on the condition of schools in the estate. The final figure available for up-front capital works is based on a number of inter-related variables and cannot yet be finalised. However, preliminary work suggests the figure is unlikely to be less than £55 million and, depending on the spend profile in the financial model, could be in excess of that amount.
3.4To place this award into context, it would take twenty-seven years of traditional Section 94 procurement to deliver a capital investment of this size. This award should enable significant capital building works in a number of schools.
3.5Our co-sponsors Partnerships UK had indicated (in the OBC) that the minimum threshold to allow an NPDO to be developed was £50 million in capital construction costs. On the basis of the offer from the Scottish Executive at least £55 million should be available for capital construction costs which should ensure that the development of the NPDO remains viable. Opinion is being sought from PUK to confirm that this reflects accurately their position and an oral update will be provided at the SPC on 15 August 2002.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic Policy Committee (Education) at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.