INTEGRATED SERVICE PLANNING AND BUDGETING 2003/2004

Agreed Committee 1 paper

Strategic Policy Committee agreed this item on Thursday 15 August 2002. Below is the council's own wording, with the papers it was decided on.

Item2

Resolved

Decision 1. Agreed the proposed timetable, process and outputs as detailed in the appendix to the report by the Director of Finance. 2. Agreed the provisional resource allocations for revenue and capital budgets and the additional savings requirements for revenue budgets. (Ref: Report by Director of Finance dated 15 August 2002, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Strategic Policy Committee

Recommendations

2.1To consider and determine the proposed timetable, process, outputs as outlined below.

2.2To consider and determine the provisional resource allocations for revenue and capital budgets and the additional savings requirements for revenue budgets.

3 DETAIL

3.1Timetable

3.1.1 An outline timetable for integrated service planning and budgeting for 2003/2004 to 2005/2006 is attached as appendix 1. In summary this covers approval of provisional resource allocations, preparation of draft service plans, revenue budgets and capital budgets, scrutiny of draft service plans and budgets, review of available resources upon announcement of local government finance settlement and setting of council tax, council house rents, service plans and budgets.

3.1.2 Draft service plans, revenue budgets and capital budgets will be available for consideration from early December. The announcement of the local government finance settlement is expected in early December. It will be early January before a thorough review of the settlement announcement is complete and an assessment made of its effect on the budgetary position. The Council tax will be set and budgets approved no later than Mid-February.

3.2Process 3.2.1 The process to be followed is in line with that adopted for the 2002/2003 to 2004/2005 cycle. Following approval of the provisional resource allocations departments will prepare both revenue and capital budgets upto the limit of the provisional resource allocations. In respect of revenue budgets schedules will be prepared detailing the savings required to bring the budget within the resource allocation. Further schedules will identify the savings required to deliver budgets under lower levels of available resources. The capital budget will largely be an exercise of introducing a new year 3 onto the current capital plan with any adjustments for rephasing of projects. It is not intended to be a complete rewrite of the capital plan. Service plans will be prepared in line with the resources included in both revenue and capital budgets.

3.3Outputs

3.3.1 Revenue budget documentation will comprise a revenue budget book in the normal format but with adjustments to reflect requirements of the Best Value Accounting Code Of Practice. As an example this will include splitting Development and Environment services into Cultural and Related Services, Planning and Development Services and Environmental Services. In addition a financial annex to the service plans will be produced. This will comprise an objective (by service eg secondary schools) and subjective (by cost type eg premises) summary of the revenue budget for a department over the 3 year planning period, a schedule of cost adjustments analysed between cost pressures and mandatory and discretionary service changes, a schedule of savings to bring budget within the resource allocation and a schedule of additional savings based on lower levels of available resources.

3.3.2 Capital budget documentation will comprise an updated 3 year capital plan in the normal format. In addition a separate document will be prepared outlining bids for unallocated capital resources. The unallocated capital resources are estimated at £469,000 for 2004/2005 and 2005/2006 based on the difference between 2003/2004 resource levels and the capital resources allocated for 2004/2005 in the current capital plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTEGRATED SERVICE PLANNING AND BUDGETING 2003/2004Report 691 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 34 attended
AB
Alasdair BovairdCouncil Staff, expected
AM
Archie MortonCouncil Staff, expected
AM
Councillor Alastair McKinlayMember, expected
AM
Councillor Allan MacaskillChair, expected
DW
Councillor David WebsterMember, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksVice-Chair, expected
RK
Councillor Ronald KinlochMember, expected
DF
Deirdre ForsythCouncil Staff, expected
ED
Elaine DochertyCouncil Staff, expected
SM
Stewart McGregorCouncil Staff, expected
JB
Jillian BrownOfficer, expected

All 34 on the meeting page

On this subject at Argyll and Bute

Search all
  1. INTEGRATED SERVICE PLANNING AND BUDGETING 2003/2004This decision
  2. Integrated Children's Services PlanAgreed
  3. Integrated Children's Services PlanAgreed
  4. Integrated servicesAgreed
  5. Integrated service plans: revenue budget 2004/05: capital 3 year rolling plan 2004/07Decided
  6. Integrated service plans: revenue budget 2004/05: capital 3 year rolling plan 2004/07Decided

More from Argyll and Bute Strategic Policy Committee

All decisions
MeetingDecisionOutcome
19 Apr 2007 Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... Noted Open
19 Apr 2007 North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... Agreed Open
19 Apr 2007 Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... Noted Open
19 Apr 2007 Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... Agreed Open
19 Apr 2007 Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies