Decision (i) To note the contents of the report. (ii) That the Directors of Education and Transportation and Property investigate methods of funding the required works and if necessary bring a report to the Strategic Policy Committee identifying any shortfall. (Reference: Report by Area Property Officer dated 18 November 2002).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
REPORT FOR HERMITAGE ACADEMY, HELENSBURGH, SECURITY SUB COMMITTEE, 18 NOVEMBER 2002.
The following arises from discussions between, Property / Facilities Management, Amenity Services, Hermitage Academy, and Strathclyde Police, in relation to Security Issues at Hermitage Academy.
Since the introduction of the new synthetic pitch and skateboarding there has been a significant rise in vandalism / misuse of property. An additional problem is the location of the caretakers’ box at the rear of the P.E. Block, which is to take into account operational requirements.
It should be noted that systems have been put in place to take into account School Security and in order to progress matters further systems will be required.
The following is a brief note of either existing or proposed:
CCTV System.
There are currently 7 operational cameras within Hermitage Academy, linked to a computer monitor and a digital recording system. The system can be extended to other facilities i.e. door entry (previously installed but not operational) and can be networked with other Secondary Schools or indeed a central base. In installing the equipment it was intended to reduce vandalism and until recently this has proved to have been successful. There was no intention for the system to be used for other areas such as pupil monitoring but since installation this facility has been developed.
In order to provide a greater coverage it is recommended that the static camera located at the corner of the P.E. Block be replaced with a dome camera which will give coverage to the rear of the property and in particular the playing fields and that the static camera be relocated overlooking the caretakers’ box which will provide for coverage of this particular area, thereby enhancing the safety / security of the occupants. It also recommended that further investigation be undertaken to obtain a control link for the cameras for the caretakers.
Discussion has taken place regarding the linking of the CCTV System with the Clydebank Control Centre. At this stage it is recommended that no further action be undertaken in respect of this. However it should be noted that Strathclyde Police are unable at this stage to operate with digital imaging and due to the requirements for first hand evidence it is recommended that an appropriate video recorder be purchased to allow the evidence to be suitable to use for possible prosecution(s).
Fencing.
Discussions have taken place with regards to the perimeter fencing and the requirement for repair / replacement. It is therefore recommended that this be undertaken as soon as possible. Remedial work to the service gate, which was damaged, it is believed by a vehicle will also be undertaken.
Throughout the course of discussions it has been recognised that due to the layout of the school there are many areas, which provide comfort for persons wishing to hide, participate in vandalism etc. Accordingly it is recommended that the perimeter of the building area be fenced, including gates etc. as appropriate. The perimeter will consist of a 2.4 metre high galvanised metal palisade fence with galvanised metal gates thereby reducing ongoing maintenance costs.
1 Barrier Gates.
Since the start of the new term building work has been completed or about to be completed at the main entrance to the school. This is in relation for a lift to be provided for disabled access. As a result of the work and an act of vandalism the main door screen has been replaced and brought forward to the façade of the building. In providing this screen there is now a requirement to restrict vehicular access to the main entrance and it is therefore recommended that a barrier gate be erected at the corner of the building adjacent to the vehicular entrance to the main door.
It is also recommended that a barrier gate be erected at the corner of the technical block to prevent unauthorised access to the playing fields, which has recently become a problem.
Lighting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.