Item10b
Resolved
Decision That the Helensburgh and Lomond Area Committee agrees that the cost of the remaining necessary works on the B831/B832 should be budgeted for in the Capital Programme to be agreed on 13 February 2003. This work is necessary to complete the Area Committee commitment to upgrade the whole of this road to maximise on the direct link to the A82 and the National Park. The Area Committee therefore refers to the full Council meeting on 13 February its request that a new line under this heading with a sum of £450,000 against it, is inserted in the Capital Programme under future years to allow this work to come forward as and when funds become available. In the interim the Area Committee requests that Roads Officers bring forward a detailed report, with costs, of short term accident prevention measures that could be taken to improve road safety. (Reference: Motion by Councillor Morton dated 20 January 2003).
Word for word from the decision Argyll and Bute published for this meeting.
Source: www.argyll-bute.gov.uk