Decision That the Council reaffirm its intention to: (a) Develop a PPP for the nominated schools; (b) Maximise the revenue support on offer from the Executive; (c) Bridge the emerging affordability gap by a combination of the strategies noted at 3.9 of the Director’s report. (Ref: Report by Project Director, submitted). The Council resolved (following a division) in terms of Section 50A(4) of the Local Government (Scotland) Act 1973, to exclude the public for part of the following item of business on the grounds that it was likely to involve the disclosure of exempt information as defined in Paragraph 1 respectively Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973. E1
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This paper provides an update and progress report on the Capital Funding Project. The paper notes that Scottish Executive approval for the revised Outline Business Case (OBC), agreed by the Council in December 2002, has been delayed. The delay has resulted from a change in accounting following the introduction of the Prudential Borrowing Regime. The effect of this change was such that it created a significant increase in the affordability gap in the financial model. This paper reports on the work undertaken to develop potential substitutions of funding to compensate for the impact of this change. The Project Management Board (membership details at Appendix 1) considered the situation at its meeting on Monday 27 January 2003 and agreed, unanimously, to recommend a package of measures designed to close the affordability gap to allow the project to proceed.
1.2This paper records the PMB recommendation which is that the strategic imperative must remain the delivery of the much overdue and much needed improvements to the schools estate at the scale and pace required. It suggests that this is best achieved by continuing with the PPP route and maximising the use of the funding already on offer from the Executive to support this development. A funding offer of £5.73M per year for 30 years, has already been made by the Scottish Executive (SE) to support the PPP route and this additional funding is not available for any other solution.
1.3Decisions require to be taken as soon as possible to avoid any further delays in the procurement process and the consequent further time/cost over-runs.
Recommendation
2.1It is recommended that the Council re-affirm its intention to:
• develop a PPP for the nominated schools; • maximise the revenue support on offer from the Executive; • bridge the emerging affordability gap by a combination of the strategies noted at 3.9.
3. DETAIL
3.1At a meeting in Balfron in October 2001 the First Minister and Council leaders agreed that improvements to school buildings were a priority and that all concerned required to provide additional funding to ensure that schools could be improved as quickly as possible. Subsequent to this meeting the SE announced additional funding support through three main routes:
• Additional funding under the new school improvement fund to assist councils on a yearly basis to make an immediate impact on their most urgent problems.
F:\moderngov\data\published\Intranet\C00000257\M00001044\AI00007801\CapitalFundingProjectNPDO0.doc 1 • Revenue support grant to assist councils to research, develop and present a viable PPP solution. • An offer of revenue funding to enable a long-term sustainable PPP solution to be applied to part of the schools estate.
3.2Argyll and Bute Council received additional funding/offers of funding from the SE under these three headings: £200k in development funding for the PPP/NPDO in 2001/02; £576k in 2002/03 for the schools improvement fund and an offer of up to £5.73M additional revenue support funding for 30 years to assist with costs of operating a PPP project for nominated schools.
3.3The combination of existing capital and revenue funding for schools, the increased school improvement fund and the possibility of developing a PPP project offered, for the first time, a realistic planned solution to the decaying fabric of the schools estate. This approach became the Council’s preferred option and secured the unanimous support of all members: this strategic development of the NPDO was commended by the Amey ‘What and How’ report as an example of good practice.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.