CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Helensburgh & Lomond Area Committee, Tuesday 13 May 2003 at 10.45am

Future of Rhu Library

Agreed Committee 2 papers

Helensburgh & Lomond Area Committee agreed this item on Tuesday 13 May 2003. Below is the council's own wording, with the papers it was decided on.

Item4l

Resolved

Decision Agreed to defer consideration of the options outlined until June 2003, to allow consultation to be undertaken with the Community Council. (Reference: Report by Head of Economic Development, Tourism & Leisure dated 4 April 2003).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Helensburgh & Lomond Area Committee

Summary

1.1The proposed extension to Rhu Primary School will have an impact on Rhu Library, which is adjacent to the school. This report outlines the options facing the library.

Recommendations

2.1That Members consider the options outlined, and instruct library staff to take the appropriate action.

Background

3.1Rhu Primary School urgently requires more space, and an extension to the building is planned, with work beginning in August 2003. As the extension will incorporate the present library area, four options are available in regard to future library provision:-

1. The library can be incorporated into the extension, but with reduced floorspace. 2. The library can be relocated elsewhere in Rhu 3. The library can be relocated into a portakabin in the school playground 4. The library can be replaced by a mobile library service.

• Option 1 would not only reduce the already small area available to the library by approximately 5 square metres, but would also compromise the requirements of the school, thus providing an unsatisfactory solution for both. • Option 2 would involve the purchase or rent of suitable space in an existing building. This would involve considerable cost implications, including provision of some new furniture and shelving. • Similar costs would be incurred with option 3, which would also reduce the area available in the school playground. • Option 4 would involve the use of Lomond mobile library on one day every fortnight. The mobile has a stock of some 7,500 books, about the same as the branch library, and could arrange to stop in several different places in Rhu, targeting those in most need. This is the preferred option from an operational and Best Value point of view. 3.2. Use of Rhu Library has been dropping steadily over the past five years. During that period issues are down by 40% and visits by 51%, a trend that is expected to continue. The new Helensburgh Library, opened in 1998, is only 2.5 miles from Rhu Library, and has drawn a considerable amount of use from it. More than one third of the population of Rhu are members at Helensburgh, considerably more than the number who use the village facility. Our 2002/03 quarterly surveys show that the average number of weekly visits to Rhu is now 51, meaning that for every hour the library is open it caters on average for fewer than four people, who borrow only nine books.

Statistics illustrating the use of all the libraries in the Helensburgh and Lomond area are attached.

4. CONCLUSIONS

4.1With steadily decreasing usage, it must be considered whether it is financially viable for the Council to relocate Rhu Library, or to replace it with an alternative service. Helensburgh Library is obviously serving the needs of many library users in Rhu.

5. IMPLICATIONS

Policy: The Council has a statutory duty to provide an adequate library service.

Financial: There is no budgetary provision at present for any of the costs associated with relocation.

Personnel: The Rhu Library assistant would be transferred to Helensburgh if Rhu Library closed.

Equal Opportunities: None

List of background papers: Statistical survey of library use.

Seamus Lalor Head of Economic Development, Tourism & Leisure 4 April 2003

For further information contact:- Andy Ewan Principal Library & Information Services Officer Tel: 01369 703214

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Future of Rhu LibraryReport 67 KB DownloadRead as text
PDF
Rhu Library figuresReport 55 KB Download

At this meeting

Whole meeting
3aArea Committee - 1 April, 2003On the agenda 3bPAN 41 - 5 February, 2003 - Memorial Park, CardrossOn the agenda 4aMonthly List of Delegated Decisions by the Director of Development and Environment ServicesNoted 4bPlanning Application - 117 West King Street, HelensburghDecided 4cPlanning Application - Selma Villa (Lower), Main Road, RhuDeferred 4dPlanning Application - Variation of Condition/Change of Use - Play Area, Redgauntlet Road, HelensburghRefused 4ePlanning Application - 36 James Street, HelensburghRefused 4fPlanning Application - High Acre, Station Road, RhuApproved 4gPlanning Application - Filter House, Whistlefield, GarelochheadNoted 4hPlanning Update Report - Memorial Park, Main Road, CardrossNoted 4iPlanning Update Report - Water Treatment Plant, Claddoch, Ardmore, By HelensburghNoted 4jDunbartonshire Economic Forum - Economic Development Strategy 2003-2008Noted 4kWest of Scotland Objective 2 Programme 2000-2006 Mid Term Evaluation - Key Future Priorities for DunbartonshireNoted
4lFuture of Rhu LibraryThis decision
4mLeisure Development GrantsDecided 5aEducation Development GrantsDecided 6aFuture Meetings and Venues for the Helensburgh and Lomond Area Committee 2003-2004Agreed 6bHelensburgh and Lomond Area Capital Funding 2003/2004Agreed 30Exclusion of Press and PublicOn the agenda 33Exclusion of Press and PublicOn the agenda 38Exclusion of Press and PublicOn the agenda 10aDelegated Decision from Council of 8 May 2003Agreed 42Exclusion of Press and PublicOn the agenda

Who was there

0 of 4 attended
ED
Elaine DochertyOfficer, expected
JM
Joe McGeerOfficer, expected
CR
Charles ReppkeOfficer, expected
NS
Nigel StewartOfficer, expected

On this subject at Argyll and Bute

Search all
  1. Future of Rhu LibraryThis decision
  2. Future of Rhu LibraryAgreed

More from Argyll and Bute Helensburgh & Lomond Area Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... Noted Open
8 Sep 2026 Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... Noted Open
8 Sep 2026 Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... Noted Open
8 Sep 2026 Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... Noted Open
8 Sep 2026 Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies