LUING FERRY - PROPOSED VIREMENT FROM CAPITAL

Approved Committee 1 paper

Strategic Policy Committee approved this item on Thursday 12 June 2003. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision Approved the funding of the additional repair costs from capital. (Ref: Report by Head of Transportation dated 12 June 2003, submitted). The Committee resolved in terms of Section 50A(4) of the Local Government (Scotland) Act 1973, to exclude the press and public for the following item of business on the grounds that it was likely to involve the disclosure of exempt information as defined in Paragraph 9 respectively Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973. E1
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Strategic Policy Committee

Summary

Early in the financial year a potential overspend has been identified within the Transportation Service. This relates to the additional repairs required to the MV Belnahua. The circumstances leading to this situation are explained in the body of the report.

Recommendations

That Members approve the funding of the additional repair costs from capital.

3. DETAIL

The vessels owned by the Council for the purposes of transporting passengers and vehicles to and from island communities are required to undergo an annual inspection in order to retain their operating certificate. This is similar to an MOT test required for motor vehicles. A certain amount of work is normally required to the vessels following the inspection and this is budgeted for under the Ferries head. It is not possible to anticipate with any degree of accuracy the amount of work that will be required to any one vessel before the results of the inspection are known. The budget is therefore based on the expectation that savings on one vessel in a particular year will offset unexpected levels of repair on another.

The inspection of the MV Belnahua this year has revealed that the vessel requires a new short engine to be fitted and also that the hull of the vessel needs to be replated. The cost of this work is estimated to be in the region of £60,000. Current levels of expenditure being incurred on the other vessels does not suggest at this time that it will be possible to make savings that will offset this unanticipated cost within the Ferries budget this year.

An overspend in the Ferries budget of £52,000 is anticipated at this time and in order to avoid this, it is proposed to fund these repairs from capital. 4. IMPLICATIONS

4.1Policy – None

4.2Financial – None

4.3Personnel – None

4.4Equal Opportunities – None

4.5Legal – None

For further information please contact Alan Brough, Support Services Manager (01546 604615).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LUING FERRY: PROPOSED VIREMENT FROM CAPITALReport 55 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 31 attended
AB
Alasdair BovairdCouncil Staff, expected
AM
Archie MortonCouncil Staff, expected
AM
Councillor Alastair McKinlayMember, expected
AM
Councillor Allan MacaskillChair, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksVice-Chair, expected
DF
Deirdre ForsythCouncil Staff, expected
ED
Elaine DochertyCouncil Staff, expected
SM
Stewart McGregorCouncil Staff, expected
GF
Councillor George FreemanMember, expected
GH
George HarperCouncil Staff, expected
AH
Councillor Alison HayMember, expected

All 31 on the meeting page

More from Argyll and Bute Strategic Policy Committee

All decisions
MeetingDecisionOutcome
19 Apr 2007 Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... Noted Open
19 Apr 2007 North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... Agreed Open
19 Apr 2007 Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... Noted Open
19 Apr 2007 Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... Agreed Open
19 Apr 2007 Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... Decided Open