Item1
Resolved
Decision 1. Agreed to accept as a standard (in addition to the existing standard bid basis) a bid based on firm costs for 3 nominated schools extrapolated for the 28 schools. 2. Agreed that the Project Director should clarify with the external legal adviser that none of the parties concerned could veto the proposed revision, and, on that basis should proceed to issue the clarification. (Verbal update by Mike Geraghty, Project Director)