VILLAGE HALLS - CAPITAL GRANT APPLICATIONS 2003-2004

Agreed Committee 1 paper

Strategic Policy Committee (Education) agreed this item on Thursday 7 August 2003. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Decision Agreed:- 1. To increase the Capital budget for Village Halls from £50,000 to £100,000 per annum from financial year 2004/2005. 2. That the grant offer to Sandbank Village Hall be increased from £7,813 to £28,438 to allow the project to proceed in the current financial year. 3. That a grant of £14,525 be awarded to Craignish Village Hall subject to securing approval of the European Regional Development Fund Bid. 4. That the Council act as lead body in the European funding application for Craignish Village Hall and Seil Village Hall when it was in a position to proceed. 5. That the Council contact the Scottish Executive asking that they undertake a review of the Local Capital Grant Scheme in consultation with local councils. 6. To note that the underwrite of £30,000 given to Tiree Village Hall in November 2002 is now required as this project is going ahead. (Ref: Report by Director of Education dated 29 July 2003, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Strategic Policy Committee (Education)

Summary

1.1Advises members of the disappointing outcome of applications made to the Scottish Executive.

1.2Recommends a change in the Capital allocated by the Council in future years in the light of the Scottish Executive decisions this year.

1.3Recommends revised priorities for the current year.

1.4Informs members of approaches made by Craignish and Seil Island Village Hall Committees for assistance from the Council in making a bid for European Regional Development Funding.

1.5The report recommends that the Scottish Executive undertakes a review of the scheme in consultation with local councils, particularly in relation to the maximum limit of grant award.

1.6Members are asked to note that the underwrite of £30,000, given to Tiree Village Hall in November 2002, in support of a European funding application is now required as this project is going ahead.

Recommendations

2.1It is recommended that the Council increase the Capital budget for Village Halls from £50,000 to £100,000 per annum from financial year 2004 - 2005.

2.2It is recommended that the grant offer to Sandbank Village Hall is increased from £7,813 to £28,438 to allow this project to proceed in the current financial year.

2.3It is recommended that a grant of £14,525 be awarded to Craignish Village Hall subject to securing approval of the European Regional Development Fund bid.

2.4The Council should act as lead body in the European funding application for Craignish Village Hall and Seil Village Hall when this is in a position to proceed.

2.5The Council should contact the Scottish Executive asking that they undertake a review of the Local Capital Grants Scheme in consultation with local

F:\moderngov\data\published\Intranet\C00000190\M00001211\AI00010486\VillageHalls0.doc 1 councils.

3. DETAIL

Scottish Executive Applications 2003 - 2004

3.1In November 2002 the Strategic Policy Committee agreed the following priorities for Capital Grant Applications for Village Halls to the Scottish Executive for 2003-2004:

Project Hall Scottish AIE Argyll & Others Total Committee Executive Bute Contribution Council 2003/04 £ £ £ £ £ £ Younger 12,000 50,000 19,000 19,000 Nil 100,000 Sandbank 5,000 20,625 7,812 7,813 Nil 41,250 Campbeltown 20,000 37,500 8,750 8,750 Nil 75,000 Guide Hall Clachan 6,000 25,000 7,000 7,000 5,000 50,000 Minard 4,000 4,800 400 400 Nil 9,600 Total 47,000 137,925 42,962 42,963 5,000 275,850

It should be noted that these figures are based on information provided by the applicants in July 2002. An up to date profile will be sought prior to assessing applications for next year as several applicants have already indicated a likely increase in costs.

3.2These have all been refused by the Scottish Executive. The reason given for refusal is that the Council “have not provided the commitment to match fund the projects up to a maximum of 25% of total expenditure.” This is disappointing; the scheme does make provision for such a maximum contribution from the Council, however, in recent years, with an increasing diversity of funders involved, we have tended to contribute less to progress more applications. This has not been raised before as an issue and most recent successful applications have had a lower than 25% contribution from the Council.

3.3It is likely that this response from the Executive reflects increasing pressure on their Local Capital Grant Scheme rather than the quality of the applications. The scheme has not been revised for over ten years. At present the maximum grant available is £100,000 based on 50% of eligible costs. This limits the maximum project costs to £200,000. At the time this limit was last revised this would approximate to the cost of a new village hall. Now the average cost of a new village hall is close to half a million pounds.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
VILLAGE HALLS: CAPITAL GRANT APPLICATIONS 2003-2004Report 79 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 33 attended
RB
Councillor Robin BanksVice-Chair, expected
SM
Sharon MacDonaldOfficer, expected
GF
Councillor George FreemanMember, expected
IG
Councillor Ian GilliesMember, expected
AM
Councillor Allan MacaskillChair, expected
DM
Councillor Duncan MacIntyreMember, expected
AM
Councillor Alastair McKinlayMember, expected
DW
Councillor Dick WalshMember, expected
NS
Nigel StewartOfficer, expected
GW
Gerry WilsonOfficer, expected
LS
Lynda SyedOfficer, expected
AM
Archie MortonOfficer, expected

All 33 on the meeting page

On this subject at Argyll and Bute

Search all
  1. VILLAGE HALLS - CAPITAL GRANT APPLICATIONS 2003-2004This decision
  2. Covid-19 micro grant fund for village halls and community organisationsNoted
  3. Capital grants for village halls - 2006/2007Decided
  4. Capital grants for village halls 2004-2005Agreed
  5. Capital grants for village hallsDecided

More from Argyll and Bute Strategic Policy Committee (Education)

All decisions
MeetingDecisionOutcome
22 Mar 2007 Getting it right for every child - draft children's services (scotland) bill consultationDecision Agreed the response to the consultation on behalf of the Council and that this be submitted to the Scottish ... Agreed Open
22 Mar 2007 Development of the argyll and bute neet strategy (not in employment, education or training)Decision To note the terms of the report. (Reference: Report by Director of Community Services dated 9 March 2007, su... Noted Open
22 Mar 2007 Revenue budget monitoring report - 31 december 2006Decision To note the Revenue Budget Monitoring position as at December 2006. (Reference: Report by Head of Strategic ... Noted Open
22 Mar 2007 Capital plan monitoring report - 31 december 2006Decision To note Capital Plan position as at 31 December 2006. (Reference: Report by Head of Strategic Finance dated ... Noted Open
22 Mar 2007 Education issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Education Issues, submitted). Noted Open