Childrens Play Areas

Approved Committee 1 paper

Helensburgh & Lomond Area Committee approved this item on Monday 3 November 2003. Below is the council's own wording, with the papers it was decided on.

Item4j

Resolved

Decision (i) Approved the revised schedule of improvement works detailed in Appendix A of the report. (ii) Noted that the Committee have agreed to pursue, as a priority, the inclusion of the Nursery Street play area in the schedule of Works. The Committee asked the SPC to include this existing play area because Nursery Street is in a social inclusion project area of one hundred plus flatted council properties where there is no other play area or open space nearby and, therefore, should have been included within the list of council owned properties. (iii) The ownership and status of the facility to be checked by the Council’s Legal Services Department.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Helensburgh & Lomond Area Committee, 6 pages

Summary

1.1Members will recall an earlier report dated 2 April 2003 which was subsequently referred to the Strategic Policy Committee on 10 July 2003.

1.2The decision of the SPC was, “To allocate the available budget equally between the four Area committees for them to prioritise the spend within their areas taking account firstly of Health and Safety issues. ”

1.3This report provides the Area Committee with an updated schedule of works for approval.

Recommendations

2.1Members approve the revised schedule of improvement works detailed in Appendix A.

Background

3.1The Council is responsible for 20 children’s play areas in Helensburgh and Lomond, with 61 pieces of individual play equipment. One of the key improvements required is the installation or replacement of impact absorbing safety surfacing.

3.2The revised schedule of work targets the primary areas of concern during this financial year, with a phased programme thereafter to be completed by 2006/2007.

3.3The deficit of £80973 for 2004/2005 is anticipated to be met from a mixture of internal and external funding. The works scheduled for 2005/2006 will not be actioned until funding is in place.

4. CONCLUSION

4.1The provision of well-designed and maintained play areas will enable Argyll & Bute Council to ensure the health and safety of children, whilst offering accessible, challenging, and creative opportunities for play. This complies with the Council’s aim of improving the quality of life for those living, working, and visiting the area. Community Involvement in the development of play space is an important part of this project. Where new development (or installation of new equipment), rather than just replacement of surfacing is planned, the views of local users will be taken into account when the selection of equipment and its location is being planned. Advice will be given to groups who come forward with ideas on play development, but until a policy on adoption of sites is debated and a conclusion reached, it is not possible to give firm undertakings that additional facilities will be adopted by the Council.

4.2Adoption of Community built and managed play areas is becoming an issue for all administrative areas with in the Council.

A report from Operational Services will go forward to the Strategic Policy Committee on this, to establish a council- wide policy on this issue. It is of paramount importance that consideration must be given to the ongoing revenue burden that such action will place on the Operational Services budget.

5. IMPLICATIONS

Policy: A report is required to Strategic Policy Committee to establish a Council Policy on the adoption of community- built Play Areas.

Financial: Additional funding will be required in 2006- 07 to complete the full programme.

Personnel: None

Equal Opportunity: None

Date of Finalisation 3 November 2003

For further information contact: Alison McIlroy, Horticultural Services Technical Officer

Telephone 01546 604360 LIST OF BACKGROUND PAPERS: 1. Minutes of Helensburgh and Lomond Area Committee – 7 October 2003 2. Report to Helensburgh and Lomond Area Committee – 7 October 2003 – “Childrens Play Areas” 3. Minutes of Strategic Policy Committee – 10 July 2003 4. Report to Strategic Policy Committee – 10 July 2003 – “Childrens Play Areas”

24 September 2003 APPENDIX A

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Childrens Play AreasReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Argyll and Bute

Search all
  1. Childrens Play AreasThis decision
  2. Childrens play areasAgreed
  3. Childrens play areaApproved

More from Argyll and Bute Helensburgh & Lomond Area Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... Noted Open
8 Sep 2026 Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... Noted Open
8 Sep 2026 Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... Noted Open
8 Sep 2026 Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... Noted Open
8 Sep 2026 Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies