Decision Agreed to note:- (a) the arrangements that have been made to alter the programme in view of the anticipated areas of slippage and variation. (b) the projected outturn in terms of expenditure and the number of properties treated, as outlined within Appendix A of the report. (c) the general progress that has been made on projects under the principal expenditure heads during the last seven years of the Council’s operation, as outlined within Appendix B of the report. (Ref: Report by Director of Community Services dated 6 January 2004, submitted and Annex B, tabled)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report advises Members of the progress that is being made on the HRA Capital Programme for 2003/2004. In addition, it confirms the arrangements that have been made to maintain expenditure at the approved level following slippage and variation in some contracts. It also outlines the progress that has been made on projects under the principal expenditure headings of the Capital Programme over the last five years.
Recommendation
2.1Members are asked to:
(a) note the arrangements that have been made to alter the programme in view of the anticipated areas of slippage and variation. (b) note the projected outturn in terms of expenditure and the number of properties treated, as outlined within Annex A. (c) note the general progress that has been made on projects under the principal expenditure heads during the last seven years of the Council’s operation, as outlined within Annex B.
3. DETAIL
3.1HRA Capital Programme 2003/2004: Members are reminded that the HRA Capital Programme for 2003/2004 was originally set at £2.707 million. This was made up as follows:
Net Borrowing Consent £1.607 Estimated Usable Receipts £0.700 Contribution from current Revenue (as agreed at the £0.100 February 2002 Housing & Social Work Committee Meeting) Carry Forward of unspent house sales receipts £0.300 Total £2.707 million
F:\moderngov\data\published\Intranet\C00000188\M00001602\AI00015441\HRACapitalProgramme0.doc 3.2. Content of the Programme: The Capital Programme has been developed to reflect the national priority issues of a) Below tolerable standard housing c) Condensation and Dampness d) Community Care, and e) Energy Efficiency.
In the circumstances, it mainly comprises of individual projects for the replacement of windows, doors and roofs, together with the provision of central heating, draught proofing, insulation and rewiring.
3.32003/2004 saw a continuation of the large increase in receipts from council house sales. The anticipated figure is approximately £1.25m as against the programmed figure of £0.7m. The Scottish Executive allow increases in receipts to be carried over to the following year. This being the case, it was considered unwise to try and increase the spending programme by the full amount part way through the financial year. Instead, it is recommended that the balance of the increase in receipt income should be carried forward to supplement the programme for 2004/2005, allowing the funds to be spent in a more considered manner.
3.4As Members will recall, it was agreed that the available resources should be allocated on a pro-rata basis for each area, depending on the number of priority 1 and 2 issues identified for attention from the ongoing property survey. Annex A demonstrates the original spending plans for each area, net of the allowances that were required for expenditure on recurring items such as private water supplies, insulation and information technology. It also projects the expenditure to the year end under the main headings, along with the number of properties that are likely to be treated. However, it should be noted that the final outcome will be dependent on factors such as weather conditions and the performance of contractors together with the level of income received in the form of usable capital receipts.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.