HRA CAPITAL PROGRAMME 2003/04

Agreed Committee 3 papers

Strategic Policy Committee agreed this item on Thursday 11 March 2004. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Decision Agreed to note:- (a) the arrangements that have been made to alter the programme in view of the anticipated areas of slippage and variation. (b) the projected outturn in terms of expenditure and the number of properties treated, as outlined within Appendix A of the report. (c) the general progress that has been made on projects under the principal expenditure heads during the last seven years of the Council’s operation, as outlined within Appendix B of the report. (Ref: Report by Director of Community Services dated 6 January 2004, submitted and Annex B, tabled)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Strategic Policy Committee

Summary

1.1This report advises Members of the progress that is being made on the HRA Capital Programme for 2003/2004. In addition, it confirms the arrangements that have been made to maintain expenditure at the approved level following slippage and variation in some contracts. It also outlines the progress that has been made on projects under the principal expenditure headings of the Capital Programme over the last five years.

Recommendation

2.1Members are asked to:

(a) note the arrangements that have been made to alter the programme in view of the anticipated areas of slippage and variation. (b) note the projected outturn in terms of expenditure and the number of properties treated, as outlined within Annex A. (c) note the general progress that has been made on projects under the principal expenditure heads during the last seven years of the Council’s operation, as outlined within Annex B.

3. DETAIL

3.1HRA Capital Programme 2003/2004: Members are reminded that the HRA Capital Programme for 2003/2004 was originally set at £2.707 million. This was made up as follows:

Net Borrowing Consent £1.607 Estimated Usable Receipts £0.700 Contribution from current Revenue (as agreed at the £0.100 February 2002 Housing & Social Work Committee Meeting) Carry Forward of unspent house sales receipts £0.300 Total £2.707 million

F:\moderngov\data\published\Intranet\C00000188\M00001602\AI00015441\HRACapitalProgramme0.doc 3.2. Content of the Programme: The Capital Programme has been developed to reflect the national priority issues of a) Below tolerable standard housing c) Condensation and Dampness d) Community Care, and e) Energy Efficiency.

In the circumstances, it mainly comprises of individual projects for the replacement of windows, doors and roofs, together with the provision of central heating, draught proofing, insulation and rewiring.

3.32003/2004 saw a continuation of the large increase in receipts from council house sales. The anticipated figure is approximately £1.25m as against the programmed figure of £0.7m. The Scottish Executive allow increases in receipts to be carried over to the following year. This being the case, it was considered unwise to try and increase the spending programme by the full amount part way through the financial year. Instead, it is recommended that the balance of the increase in receipt income should be carried forward to supplement the programme for 2004/2005, allowing the funds to be spent in a more considered manner.

3.4As Members will recall, it was agreed that the available resources should be allocated on a pro-rata basis for each area, depending on the number of priority 1 and 2 issues identified for attention from the ongoing property survey. Annex A demonstrates the original spending plans for each area, net of the allowances that were required for expenditure on recurring items such as private water supplies, insulation and information technology. It also projects the expenditure to the year end under the main headings, along with the number of properties that are likely to be treated. However, it should be noted that the final outcome will be dependent on factors such as weather conditions and the performance of contractors together with the level of income received in the form of usable capital receipts.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1HRAAppendix 1HRA 70 KB Download
PDF
HRA CAPITAL PROGRAMME 2003/04Report 96 KB DownloadRead as text
PDF
HRA Cap Prog Annex BAppendix 78 KB Download

At this meeting

Whole meeting

Who was there

0 of 31 attended
AM
Councillor Alastair McKinlayMember, expected
AM
Councillor Allan MacaskillChair, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksVice-Chair, expected
DF
Deirdre ForsythCouncil Staff, expected
ED
Elaine DochertyCouncil Staff, expected
GF
Councillor George FreemanMember, expected
GH
George HarperCouncil Staff, expected
AH
Councillor Alison HayMember, expected
DH
Douglas HendryCouncil Staff, expected
DK
Councillor Daniel KellyMember, expected
DL
Danny LongwillCouncil Staff, expected

All 31 on the meeting page

On this subject at Argyll and Bute

Search all
  1. HRA CAPITAL PROGRAMME 2003/04This decision
  2. Hra capital programme 2005/06Noted
  3. Hra capital programme 2006/07, 2007/08, 2008/09 - allocation of resources & prioritisation of projects for inclusionDecided
  4. Hra capital programme 2004/2005Decided
  5. Hra capital programme 2005/08 - allocation of resources & prioritisation of projects for inclusionDecided
  6. Hra capital programme 2004/07Agreed

More from Argyll and Bute Strategic Policy Committee

All decisions
MeetingDecisionOutcome
19 Apr 2007 Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... Noted Open
19 Apr 2007 North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... Agreed Open
19 Apr 2007 Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... Noted Open
19 Apr 2007 Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... Agreed Open
19 Apr 2007 Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... Decided Open