Decision To recommend to Council that the scheme for the replacement of Mill Street Bridge, Rothesay be included as part of the Bridge Replacement Programme 2004/5 and that the cost of the combined works be met from adjustment to the £500,000 included in the 2004/5 Capital Programme for Roads and Lighting. (Reference: Report by Head of Transportation and Infrastructure dated 29 April 2004, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to inform the Committee of the closure of Mill Street Bridge, Rothesay, and to seek approval for the allocation of funding from the Capital Programme in 2004/05 to have the structure replaced.
Recommendation
2.1The Committee approve the inclusion of a scheme for the replacement of Mill Street Bridge, Rothesay as part of the Bridge Replacement Programme 2004/05 and consider two options for funding the works:
1. Slip expenditure on A816 Kintraw Bridge Approach Wall into 2005/06 with subsequent adjustments in later years to ensure that budget line remains within the capital budget allocation, and additionally the Capital Flood Prevention Programme be adjusted to allow works to be undertaken at the same time in the waterway adjacent to the bridge to improve flow in the burn and reduce the recurrence of flooding in the area.
2. The cost of the combined works is met from adjustment to the £500,000 included in the 2004/05 Capital Programme for Roads and Lighting.
Background
3.1On 13 December 2003, a hole appeared in the carriageway over Mill Street Bridge and the road was closed. On investigation it was discovered that a section of the masonry arch had collapsed.
3.2The fill above the arch collapse was cleared and a repair attempted. Before placing any backfill, divers carried out a structural survey of the underside of the bridge and this revealed that the collapse had been more extensive than at first thought with considerable loss of arch stones. The conclusion was therefore that a repair from above the structure was not feasible.
3.3The B878 is the main route out of the town to west Bute, is a bus route and is widely used by pedestrians and by children travelling to and from school. The surrounding roads currently being used as a diversion are not suitable for larger vehicles, especially John Street which is narrow with poor junctions at both ends. The option of not repairing the bridge and permanently closing the road has therefore been discounted.
3.4Following consultation with a specialist contractor and a further detailed inspection, the following options were considered:
(a) Leave the existing arch structure in place and install two steel pipes beneath it with the voids between the arch and pipes being filled with concrete; (b) Demolish the existing structure and replace with precast concrete box culvert units; Option (a) resulted in a considerable reduction in the waterway area beneath the bridge and could have led to flooding upstream. This option was therefore discounted.
3.5It is therefore recommended that the existing bridge is demolished and replaced with precast concrete box culvert units at an estimated project cost of £90,000.
3.6Because of the time it will take to finalise a design, issue tenders and appoint a contractor, arrangements have been made to backfill the excavation in the carriageway and install a temporary steel structure over the bridge to allow the road to be re-opened to single-way traffic. However, once the contractor takes possession of the site to replace the bridge, the road will have to be closed to all traffic for the duration of the bridge works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.