Resolved
Decision To note and endorse the contents of the report. (Reference: Report by Head of Planning dated 18 May 2004)
Helensburgh & Lomond Area Committee noted this item on Tuesday 1 June 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To note and endorse the contents of the report. (Reference: Report by Head of Planning dated 18 May 2004)
1.1This paper outlines my Department’s Development Control performance with respect to processing applications as set against the performance targets set by the four Area Committees.
1.2In addition to reviewing the Council wide performance from April 2003 to March 2004, this report also identifies the performance and sets targets for each of the four decentralised areas.
1.3Unfortunately, my Department failed to reach the target of processing 72% of all applications within two months. Performance was also down on previous years slipping back from last years high of 69% to 64%.
1.4Similarly, with respect to householder applications, my Department failed to reach the target of processing 90% of householder applications within two months, which had been achieved over the last two years. In this regard my Department processed 88% of householder applications within two months, which represents a 2% drop in performance.
2.1It is recommended that Members: -
a) Note and endorse the contents of the report. b) Agree to a Council wide target of 72% of all applications being processed within two months for the period April 2004 to March 2005. c) Adopt the Scottish Executives’ target of deciding 90% of householder applications within two months. d) Agree that the targets set out below be adopted for each of the decentralised areas for the period April 2004 to March 2005.
Bute and Cowal 77% No change Helensburgh and Lomond 79% +1% Oban, Lorn and the Isles 65% No change Mid Argyll, Kintyre and Islay 66% No change
3.0COUNCIL WIDE DEVELOPMENT CONTROL PERFORMANCE APRIL 2003 – MARCH 2004
3.1TABLE 1. TARGETS AND ACHIEVEMENTS SINCE 1996
TABLE 1: TARGETS AND ACHIEVEMENTS SINCE RE-ORGANISATION % OF ALL APPLICATIONS DEALT WITH WITHIN 2 MONTHS YEAR APPLICATIONS APPLICATIONS TARGET ACHIEVED RECEIVED DETERMINED 1996/97 1402 1162 57% 46% 1997/98 1482 1355 57% 63% 1998/99 1519 1318 67% 67% 1999/2000 1507 1340 69% 65.3% 2000/2001 1529 1252 68% 66% 2001/2002 1614 1420 71% 66% 2002/2003 1692 1490 71% 69% 2003/2004 1813 1512 72% 64% 3.2 Development Control Performance across the Council wide area has slipped back significantly from last years high of 69% to 64%. In addition to slipping back in terms of last year’s performance, the current years figure is 8% below target.
3.3Notably the number of applications dealt with continues to increase since 1996 rising from 1162 to the current level of 1512, together with significant increases in applications received which are at an all time high of 1813, compared to 1402 in 1996/97. This continuing increase is notwithstanding that the applications within the National Park Area have now been dealt with by the Park Authority for the last year. The most significant increases in applications relate to the Mid Argyll, Kintyre and Islay and Oban, Lorn and the Isles decentralised areas. (See tables 2 and 3 below).
3.4It is within the Mid Argyll, Kintyre and Islay and Oban, Lorn and the Isles areas where the ever-increasing number of applications is having the greatest effect on performance. Additionally, once the full effect of the current Draft Local Plan is experienced in terms of additional applications, this is likely to impact most significantly on these two decentralised areas.
3.5Notwithstanding the above, the drop in performance is disappointing, although this is set against increasing applications, the initial effects of a “development based” draft Local Plan, staff changes and new staff becoming familiar with the Council’s practices and procedures. Staff changes in the Oban, Lorn and the Isles area in particular is impacting in performance.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Development Control Performance Monitoring Council Wide and Decentralised Area Team PerformanceReport | 111 KB | DownloadRead as text |
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... | Noted | Open |
| 8 Sep 2026 | Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... | Noted | Open |
| 8 Sep 2026 | Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... | Noted | Open |
| 8 Sep 2026 | Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... | Noted | Open |
| 8 Sep 2026 | Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.