Resolved
Decision Having considered the objectives, options and risks - 1. To add to the approved Capital Programme on the basis of increasing the charges to Shell to cover the additional loan charges over 10 years as outlined in paragraph 7 of the submitted report. 2. To authorise the Director of Development Services to invite tenders for a professional services contract and to delegate powers to the Director to accept a preferred consultant. (Reference: Joint Report by the Director of Development Services and Head of Strategic Finance dated 15 July 2004, submitted).