Decision The Area Committee agreed in general to the lists of Schemes subject to the following amendments: Quick spend schemes – windfall money – Bute and Cowal Project 39 – West Princess Street & Store Lane, Rothesay – Safety Benefit amended to a factor of 10, Overall Score increased to 19. Future Strategic Schemes as Proposed by Area Committees Project 17 – Port Ann/Otter Ferry – Bute and Cowal Area Committee did not propose and do not support such a scheme. Project 23 – Dunoon Pier – Strategic Importance factor increased to 10, HITRANS Score increased to 5, Overall Score increased to 37. The Area Committee stressed that the retention of Dunoon pier is a Cowal priority. HITRANS/WESTRANS Quick Spend Schemes 2004 – 2005 List approved as submitted Area “waterfront” type schemes The Dunoon Seafront/Waterfront Development should be included in these submissions. (Reference; Report by Head of Transportation & Infrastructure, dated 24 November 2004 - submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The purpose of this report is to ask the Area Committee to agree a mechanism which will enable Transportation priorities to be set in order to promote schemes with Hitrans or Westrans, the voluntary Regional Transport Partnerships, in the event that funding opportunities arise through these Partnerships.
Recommendations
That the Committee
1. Agree the factors and weighting used to prioritise the various projects which were originally put forward.
2. Note the attached appendix which illustrates the effect of ranking Area proposals using the various factors as described..
3. Note the intention to prioritise proposals across the Council Area using the weighting mechanism described, and make provision in the current capital programme for the preparation of a number of these proposals, in order that windfall funding opportunities may be grasped.
4. Decide whether it is appropriate to include Area ‘waterfront’ type schemes, which may have a limited Transportation element.
Background
Over the course of the last 3 years, the Council has benefited from approximately £1.5m of funding from the voluntary transport partnerships, Hitrans in particular. Given the Executive’s intention to formalise these partnerships, it is highly likely that this funding stream will grow. The Policy Development group have been anxious to prepare a list of transportation schemes which would place the Council in a strong position to take advantage of any such future funding, and previously asked all four Area Committees to consider their transportation networks, and advise which would be their priority schemes. The Committees were asked to consider two situations – larger, strategic
F:\moderngov\data\published\Intranet\C00000242\M00001959\AI00020799\AreaCommitteeHiWeBCJan050.doc 1 of 4 12 January 2005 schemes and smaller proposals which would be suitable for ‘quick spend’ windfall type monies. The Areas have put forward a number of schemes in each category, which have been ranked by the Policy Development Group in terms of the following factors
a) Strategic Schemes
1. Economic Benefit to the area 2. Strategic Importance 3. The Council’s ability to influence the outcome (land under Council’s control, for example) 4. Alignment with Hitrans/Westrans funding themes 5. Cost, with lower costing schemes accorded the higher weighting.
Factor 1 has been scored as Low, medium or high, and allocated 3,9 or 15 marks respectively. Factor 2 has been scored similarly but with reduced weighting and given 2, 6 or 10 marks. Factors 3 and 4 are given 1,3 or 5 marks. Factor 5, the cost, is banded as over £5m, £1m - £5m and under £1m and given 1.2 or 3 marks.
Maximum available marks - 38
b) Quick spend schemes
1. Community Benefit 2. Safety benefit 3. Council influence on project 4. Alignment with Hitrans or Westrans funding themes.
These factors are scored similarly, Factor1, Factor 2 and factors 3 and 4 having 15, 9 and 3 points, 10, 6 and 2 points and 5,3 and 1 point.
Maximum available marks - 35
The attached appendix illustrates the effects of applying the weighting to the various factors as described.
Waterfront Developments
During discussion of the various proposals at the PDG meeting of 22nd November, Dunoon’s Waterfront development was identified as a scheme with a transportation component which had not been put forward by the Area Committee as one of their strategic projects. Advice given earlier by officers was that the Waterfront scheme as constituted
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.