Decision Noted the following implications of this essential work being undertaken: (i) During the period of refurbishment as Thomson Court and Struan Lodge are unable to offer respite care, alternative local arrangements will be put in place. (ii) Resident numbers will require to be reduced in each of the units while refurbishment work is underway. This is planned to ensure minimal disruption to residents who may have to move beds within the Care Home whilst their bedroom area is refurbished. (iii) There will be a resultant loss of income as bed numbers are temporarily reduced over the period of the refurbishment. This is projected as £53,370.86. (iv) Where there is staff capacity due to reduced resident numbers, the staff have been consulted and will provide care to older people living at home during this period of refurbishment. (v) The work will be phased and is planned to commence in February 2005 and conclude in July 2005. (vi) On conclusion the Council Care Homes will be able to provide single care as expected by the Care Commission. Additional staffing costs will be required to deliver this care and moving to the standard of operation will have manpower implications for the Council. This will be the subject of a separate report to a future Strategic Policy Committee meeting. (Ref: Report by Director of Community Services dated 10 January 2005, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report details the arrangements for managing the refurbishment of Five Local Authority Care Homes which are undergoing significant refurbishment to bring them up to Care Commission Standards for Single Care Accommodation over the next eighteen months. Capital expenditure for this purpose has previously been agreed by Committee.
1.2The new facilities will offer all residents single room en suite accommodation. These improvements will greatly assist staff to provide a high quality of care to the increasingly more dependent older people admitted to Local Authority care homes.
1.3These environmental changes will contribute significantly to the aim of providing high quality, benchmark Single Care services for older people across Argyll and Bute Council and assist us in meeting essential older persons Strategy requirements.
Recommendations
2.1That Members note the undernoted implications of this essential work being undertaken.
(i) During the period of refurbishment as Thomson Court and Struan Lodge are unable to offer respite care, alternative local arrangements will be put in place. (ii) Resident numbers will require to reduce in each of the Units while refurbishment work is underway. This is planned to ensure minimum disruption to residents who may have to move beds within the Care Home whilst their bedroom area is refurbished. (iii) There will be a resultant loss of income as bed numbers are temporarily reduced over the period of refurbishment. This is projected as £53,370.86 (see Appendix A). (iv) Where there is staff capacity due to reduced resident numbers, staff have been consulted and will provide care to older people living at home during this period of refurbishment. (v) The work will be phased and is planned to commence in February 2005 and conclude in July 2005. (vi) On conclusion the Council Care Homes will be able to provide Single Care as expected by the Care Commission. Additional staffing costs will be required to deliver this care moving to this standard of operation will have manpower implications for the Council and this will be the subject of a separate report to a future Strategic Policy Committee meeting.
Background
3.1Five Local Authority establishments offering residential care for older people are to undergo substantial refurbishment to meet the requirements of the Care Commission between February 2005 and August 2005. The facilities concerned are:
3.2The remaining two Dunaros, Mull and Eadar Glinn, Oban require replacement as they are not “fit for purpose”.
3.3Dunaros, Mull will be replaced by the Mull Progressive Care Centre and timescales for this are yet to be set.
3.4Discussions with West Highland Housing are underway about the possibility of reprovision of Eadar Glinn with a 12 place Housing with Support facility. These talks are at an early stage and we are awaiting the outcome of a meeting of West Highland Housing at the end of January 2005, which should give an indication, in principle as to whether they can provide funding for this development.
3.5It is anticipated that when work is completed all of the residential services will provide Single Care Accommodation (residential and nursing care according to individual need) for Older People.
4. INTERIM ARRANGEMENTS
4.1The following measures are proposed to minimise disruption to service users during the refurbishment.
• A moratorium on admissions. (This will hopefully free up sufficient beds to enable work to be carried out on designated wings in each establishment, with minimum disruption for service users requiring a temporary move of bed within the Care Home)
• Some residential workers will temporarily support intense community care packages
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.