Resolved
Decision To recommend to the Council that:- 1. The scope of the Project is revised to include ten schools on five sites: Hermitage Academy; Dunoon Grammar; Rothesay Joint Campus – comprising Rothesay Academy and Rothesay Primary; Lochgilphead Joint Campus – comprising Lochgilphead High School, Lochgilphead Primary and Whitegates Learning Centre; Oban Primary Campus – comprising Rockfield Primary, St. Columba’s RC Primary, and Drummore Learning Centre; 2. That the remaining schools are removed from the Project and are dealt with under the Council’s Capital Programme: Tiree Joint Campus; Cardross Primary; Rosneath Primary; Kilcreggan Primary; Arrochar Primary; Luing Primary 3. The Council endorse the revised scope at 1 and 2 above and instruct the Project Team to deliver this affordable and VfM scoped Project by Financial Close on 31 March 2005 Councillor Hay, having moved an amendment which failed to find a seconder, required her dissent to be recorded. Councillor Freeman, having moved an amendment which failed to find a seconder, required his dissent to be recorded. (Ref: Report by Project Management Board, Report by Project Director dated 31 January 2005 and Appendices submitted, updated Appendix 6, tabled)