Decision 1. To note the monitoring arrangements in place until the end of 2004 and agree that future external auditing and monitoring of the PPP Contract be contained as part of the normal reporting of the Council’s performance as required under the second award of Strategic Waste Funding in 2004. 2. To instruct the Director of Operational Services and relevant staff to take forward the Contract Review process with Shanks during the next financial year, taking account of any service changes and performance issues outlined in the submitted report or prior to the Review; and to report further to this Committee on the outcome of that Review in 2006. 3. To instruct the Director of Operational Services to bring a report to this Committee with regard to the commitment of funding from the Highlands and Islands Partnership Programme (HIPP) support awarded in 2001. (Ref: Report by Director of Operational Services dated 1 April 2005, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report is to update Members on the current position with the Waste Management PPP Contract and, following a remit from the SPC in December 2004, to outline contractor performance in line with the original contract as issued.
Recommendations
2.1Members note the monitoring arrangements in place until the end of 2004 and agree that future external auditing and monitoring of the PPP contract be contained as part of the normal reporting of the Council’s performance as required under the second award of Strategic Waste Funding in 2004.
2.2That the Director of Operational Services and relevant staff are instructed to take forward the Contract Review process with Shanks during the next financial year, taking account of any service changes and performance issues outlined in this report or prior to the Review; and to report further to this Committee on the outcome of that Review in 2006.
2.3That the Director of Operational Services is instructed to bring a report to this Committee with regard to the commitment of funding from the Highlands and Islands Partnership Programme (HIPP) support awarded in 2001.
3. DETAIL
3.1Specification as Issued
3.1.1 The Council entered into the Waste Management PPP for three main purposes:
1. To fulfil the statutory obligations of the Council under the Environmental Protection Act 1990 and relevant European Directives by providing for a proper network of sites to receive, treat and dispose of waste for which the Council has a duty under our legislative remit; 1 of 14 06 April 2005 2. To provide major upgrading of waste disposal facilities in part of our Council’s area to the standards required by the Scottish Environment Protection Agency (SEPA);
3. To ensure that the specific requirements of new waste diversion and recycling targets are met within the contract area.
3.2Monitoring Arrangements
3.2.1 While the contract is mainly based on the outputs provided, there are a number of ongoing contract monitoring mechanisms;
1. Day-to-day overview of how sites operate, in particular availability of disposal facilities, proper use and maintenance of recycling and civic amenity sites and dealing with requests for ad hoc services such as scrap car uplifts;
2. A contractual arrangement for Contract Development Group meetings on a regular basis, supplemented by operational meetings at a management level from both the Council and Shanks;
3. Up until last year, an annual appraisal of contract performance against specified outputs, carried out by an independent consultancy; this review to form part of the approvals process for the European funding element of the infrastructure works committed under the PPP.
3.2.2 Appendix I to this report is the executive summary of the independent consultant’s report for 2004.
3.2.3 In terms of future monitoring, the arrangements for day-to- day links to Shanks and periodic joint meetings will continue, but it is suggested that the current consultancy work carried out specific to the PPP is not renewed. Rather, that the overall performance of the PPP within Argyll & Bute’s wider waste management performance is addressed as part of the functions to be carried out by the external audit of projects supported by the second tranche of Strategic Waste Funding. Recommendation 2.1 addresses this point.
3.3Current Performance
2 of 14 06 April 2005 3.3.1 In broad terms:
1. Shanks’ performance, in meeting infrastructure improvement requirements on the sites operated by them, has been generally satisfactory, if slightly delayed and with occasional problems – recent instances of odour complaints at Dalinlongart, for example. However, there are outstanding issues on improvement works to island sites. At these sites Shanks had some responsibility for upgrading basic infrastructure, albeit the Council continues to operate the sites. Some of these issues leave the Council vulnerable to SEPA prosecution.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.