Decision 1. To note the progress on the Procurement Project. 2. To agree the proposed governance and contractual arrangements connected with the Procurement Project, as outlined in the submitted report. (Ref: Report by Chief Executive dated 27June 2005, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
This report updates the Strategic Policy Committee as to progress on the Pathfinder broadband procurement project which aims to provide high capacity broadband links to schools, libraries and other council buildings throughout the Highlands and Islands. The Strategic Policy Committee is asked to note progress on the procurement and agree the proposed governance and contractual arrangements
1. Introduction
1.1The project to secure broadband connectivity to schools and other local authority sites was transferred from the Scottish Executive to local authority control in September 2005. The Highland Council acts as the lead on behalf of the six Highlands and Islands Authorities. The current proposals are for the procurement of managed services from a leading telecommunications company. The procurement route is by Invitation to Negotiate which will be issued to a limited number of telecommunications providers who satisfy the requirements of a Pre Qualification Questionnaire (PQQ). The total estimated budget for the 5-7 year contract will be £70m, with £63m coming from the Scottish Executive. The arrangement for the Western Isles is that £1m of the £63m will be ring-fenced to allow a “pathfinder equivalent” upgrade to the Connected Communities network to take place during 2006.
1.2Project Benefits
The main benefits of the project are seen as:
• Permitting the full local delivery of the Scottish Schools Digital Network (SSDN) which is currently being rolled out by Learning and Teaching Scotland. • Enabling the effective delivery of e-government initiatives such as Customer First and the Efficient Government Strategy.
The project will result in the provision of additional telecommunications infrastructure throughout the Highlands and Islands which could have benefits for other public sector bodies and the private sector. This, however, is not a primary driver for the procurement.
1/4 2.0 Project Administration, Proposed Governance and Contractual Arrangements
The project is run by a Project Board consisting of the Chief Executives of Highland, Moray, Western Isles, Argyll and Bute with the Deputy Chief Executive of Orkney and the Head of Development Resources of Shetland. Arthur McCourt is the Project Director. The Board meets on average every 6 weeks. A dedicated Project team, consisting of three members of staff employed by The Highland Council in Inverness was appointed in March/April 2005:
Technical Advisors to the project have been appointed (Masons) and procurements for the necessary specialist legal and technical advice are commencing. Robert Craig has been appointed as an observer on the Board to provide a direct link to the Minister for Education and Young People, Peter Peacock MSP.
Current Member Governance arrangements are through the Highlands and Islands Convenors/Leaders Group. In this regard, the Project Board’s recommendations are that;
a. The governance arrangements continue to be by way of the Highlands and Islands Convenors/Leaders Group b. That the six partner Councils enter into a Minute of Agreement setting out the Governance proposals and the intention that the contracting arrangements be that each Council enter into a separate but complementary contract with the supplier, under the guidance and supervision of the Project Board. c. And that these arrangements would be submitted to each Council for formal approval.
1.4State Aids
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.