Decision 1. In view of the success of bids for match funding of the Oban High Community Sports Project, the Committee agreed to a virement of £100,000 to the Kenny MacIntyre Memorial Sports Facility at Tobermory to allow the project to progress immediately. 2. To request that the Playing Fields Development Unit undertakes a review of all completed projects and that a report on the management, performance and sustainability of completed projects be brought to a future meeting of the Strategic Policy Committee. (Ref: Report by Director of Operational Services dated 11 August 2005, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report updates Members on progress with the Council’s Match Funded Playing Fields Capital Programme and proposals for monitoring the performance of existing and future facilities.
Recommendations
It is recommended that:
2.1In view of the success of bids for match funding of the Oban High Community Sports Project, the Committee agree a virement of £100,000 to the Kenny MacIntyre Memorial Sports Facility at Tobermory, to allow this project to progress immediately.
2.2The Playing Fields Development Unit undertakes a review of all completed projects and that a report on the management, performance and sustainability of completed projects is brought to a future meeting of the Strategic Policy Committee.
3 PLAYING FIELDS CAPITAL PROGRAMME
3.1At the Strategic Policy Committee of 3rd June 2004 members agreed to increase the playing fields capital allocation to offset the reduction in the budget for future grant aid available from the Sportscotland Lottery Fund. The Capital Programme allocations for 2005/06 and 2006/2007 were £602,000 and £407,000 respectively.
3.2The main projects to be funded in the current financial year were Oban High Community Sports Facility and the Kenny MacIntyre Memorial Sports Facility at Tobermory, along with Kirkmichael in Helensburgh, which was to be funded from the Capital Receipt from the sale of the existing blaes pitch for housing.
F:\moderngov\data\published\Intranet\C00000188\M00002102\AI00023480\PlayingFieldsSustainabilitySPC110 1 8050.doc 3.3 The Oban High Community Sports Facility is the Council’s top priority project for 2005/6. The scope for undertaking the Kenny MacIntyre Memorial Sports Facility at Tobermory in addition to the Oban High project this financial year will be determined by capital funding and seasonal constraints on construction activities.
4 EXTERNAL MATCH FUNDING
4.1The Oban High project was approved for funding under Sportscotland’s Regional Facility Strand and was awarded £334,000 including £60,000 match funding from the Big Lottery fund, against a maximum projected income of £200,000 under the community strand. There is therefore a projected surplus on the Oban project of £119,000 in 2005/06 and £15,000 in 2006/07, as shown on Appendix 1.
4.2At the time of the award for Oban High, discussions with Sportscotland indicated that an application for additional funding for the Kenny MacIntyre Memorial Sports Facility at Tobermory was unlikely to be supported in the short term. The Tobermory project did however benefit from £69,000 Big Lottery Funding and the Kenny MacIntyre Memorial Trust has so far pledged £31,000. Together with the Council’s agreed contribution of £139,000, this leaves a shortfall of £100,000.
5 PROGRESS
5.1The Oban project was tendered in June successfully in accordance with the capital programme dates. A start date of 25th July was agreed, with completion programmed for early November.
5.2Following the Oban High tender return and discussion with the Council Spokesperson, the Tender Documents for the Tobermory Project were issued on 8/7/2005 for return on 1/8/05. Though no guarantee was given as to their acceptance, this time table will allow the delivery of the Tobermory Project within this financial year, subject to no unforeseen circumstances.
5.3As there is currently a surplus of capital identified for Oban High, scope now exists, subject to acceptable tender returns, for this capital surplus to be vired to the Kenny MacIntyre Memorial Sports Facility. This will allow the project to be completed this year as originally planned. In addition, there may be scope for any remaining funding in 2006/07 to be transferred to the Tarbert project, which is next in line for capital funding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.