Decision HRA CAPITAL PROGRAMME 2005/6 The Council – Noted the arrangements that have been made to alter the programme in view of the anticipated areas of slippage and variation. Noted the projected outturn in terms of expenditure and the number of properties treated, as outlined within Annex A to the report by the Director of Community Services considered by the Committee. Noted the general progress that has been made on projects under the principal expenditure heads during the last six years of the Council’s operation, as outlined within Annex B to the report by the Director of Community Services considered by the Committee. HRA CAPITAL PROGRAMME 2006/7, 2007/8, 2008/9 – ALLOCATION OF RESOURCES AND PRIORITISATION OF PROJECTS FOR INCLUSION The Council approved – The recommendations which will enable the HRA Capital Programme to be set at a minimum of £2.457 million for 2006/7 and at £2.307 million for 2007/8 and 2008/9. The proposals for the prioritisation of projects for inclusion within the Capital Programme. PROPOSAL FOR RENT INCREASE The Council resolved as follows:- 1. That the rents for properties on the Housing Revenue Account be increased by an average of £1.66 per week (3.5%). 2. That in order to achieve the additional income, the notional average rents of Council Houses be increased as follows: Size of Property Average Weekly Rent 2005/06 Proposed Annual Increase Proposed Weekly Increase * Average Weekly Rent 2006/07 1 / 2 Apts 41.68 73.00 1.46 43.14 3 Apts 47.25 82.50 1.65 48.90 4 Apts 52.21 91.50 1.83 54.04 5 + Apts 55.88 98.00 1.96 57.84 GT Sites + 31.60 55.50 1.11 32.71 Garages 31.10 5.50 0.11 3.21 *All “Weekly” figures relate to the 50-week rent year. + GT = Gypsy/Travelling Persons Sites (Ref: Reports previously circulated to Strategic Policy Committees of 19 and 26 January 2006)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report advises Members of the progress that is being made on the HRA Capital Programme for 2005/2006. In addition, it confirms the arrangements that have been made to maintain expenditure at the approved level following slippage and variation in some contracts. It also outlines the progress that has been made on projects under the principal expenditure headings of the Capital Programme over the last five years.
Recommendation
2.1Members are asked to:
(a) note the arrangements that have been made to alter the programme in view of the anticipated areas of slippage and variation. (b) note the projected outturn in terms of expenditure and the number of properties treated, as outlined within Annex A. (c) note the general progress that has been made on projects under the principal expenditure heads during the last six years of the Council’s operation, as outlined within Annex B.
3. DETAIL
3.1HRA Capital Programme 2005/2006: Members are reminded that the HRA Capital Programme for 2005/2006 was originally set at £2.457 million. This was made up as follows:
3.2Content of the Programme: The Capital Programme has been developed to reflect the national priority issues of a) Below tolerable standard housing c) Condensation and Dampness d) Community Care, and e) Energy Efficiency.
F:\moderngov\data\published\Intranet\C00000257\M00002259\AI00025960\HRACapitalProgramme20052006report0.doc In the circumstances, it mainly comprises of individual projects for the replacement of windows, doors and roofs, together with the provision of central heating, draught proofing, insulation and rewiring.
3.32005/2006 has seen a continuation of the increase in the value of receipts from council house sales. The anticipated figure is approximately £1.00m as against the programmed figure of £0.85m. This has offset the rise in tender levels experienced this year. There continues to be a general rise in the level of tenders over the past year and this was particularly evident in the Mid Argyll, Kintyre and Islay area.
3.4As Members will recall, it was agreed that the available resources should be allocated on a pro-rata basis for each area, depending on the number of priority 1 and 2 issues identified for attention from the ongoing property survey. Annex A demonstrates the original spending plans for each area, net of the allowances that were required for expenditure on recurring items such as private water supplies, insulation and information technology. It also projects the expenditure to the year end under the main headings, along with the number of properties that are likely to be treated. However, it should be noted that the final outcome will be dependent on factors such as weather conditions and the performance of contractors together with the level of income received in the form of usable capital receipts.
3.5Treatment of Slippage and Variations: During the course of the year, expenditure on private water supplies and insulation has been less than anticipated. This is in the main due to the difficulties in resolving issues with private water supplies where private owners are involved and the cavity wall insulation programme coming to an end. In general, these savings have allowed increased expenditure on new central heating installations and rewiring. Additional grant funding was also received from Supporting People Rent Pool which allowed a further increase in the provision of heating systems. The increased council house sale receipts, referred to in the previous section, have also been allocated, in part, to permit the provision of additional windows and doors.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.