HELENSBURGH PARTNERSHIP - ESTABLISHMENT AND FUNDING SUPPORT

Agreed Committee 1 paper

Strategic Policy Committee agreed this item on Thursday 13 April 2006. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision 1. Agreed to allocate £100,000 in 2006/07 to the Helensburgh Partnership, subject to the receipt of quarterly monitoring reports on their financial and operating performance against the various priorities and targets in their Business Plan to the Director of Operational Services as link Director; and 2. Agreed the principle of continued funding subject to the Council Budget process in 2007/08 and satisfactory performance by the Partnership with half yearly reports being submitted to the Strategic Policy Committee. (Ref: Report by Director of Operational Services dated 4 April 2006, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Strategic Policy Committee

Recommendations

2.1That Members allocate £100,000 in 2006/07 to the Helensburgh Partnership, subject to the receipt of quarterly monitoring reports on their financial and operating performance against the various priorities and targets in their Business Plan to the Director of Operational Services as Link Director. Further, that subject to the Council Budget process in 2007 and 2008 and satisfactory performance by the Partnership, the principle of continued funding on the basis of the foregoing be agreed.

3. DETAILS

3.1The Helensburgh Partnership is chaired independently, but has representation from both the Council (three members) and Scottish Enterprise Dunbartonshire (one member), together with other board members from the Chamber of Commerce, local Community Council and the Retailers Association.

3.2The partnership board was established following public advertising for a chairman at the end of last calendar year and it has met thrice since then in order to establish its constitution and standing orders.

3.3The standing orders of the partnership have been reviewed by our Strategic Finance and Legal staff and are deemed to be satisfactory. Procurement of goods and services is subject to proper tendering requirements, or the procurement rules in place within either the Council or SED.

3.4The operation of the Partnership is subject to an annual review by both joint funding bodies. The initial budgetary provision is predicated on the Business Plan produced during August 2005, which was presented jointly to the Council and SED. SED have committed funding already, a considerable additional benefit to the area. The indicative budget (Annex 3 from the Business Plan) is appended to this report. At the time of the Business Plan’s production some of the Council’s contribution was seen as being in kind but taking account of the difficulty of office accommodation and staffing allocation, the provision of funding to allow self-funding of these by the Partnership is more straightforward.

3.5“Following the Public Pound” requires arrangements between the Council and arms-length external organisations to demonstrate that Council support should be able to show a relationship to Council priorities and performance against achievement of outcomes. The requirement in recommendation 2.1 allows these necessary monitoring arrangements to be implemented.

3.6The board are currently in the process of advertising for an Executive Director, following which they will require expenditure on a regular monthly basis. The job description, specification and guide for this post has been agreed by Council representatives and SED and again broadly follows the scope of the job suggested in the business Plan for the Partnership.

3.7The small amounts of expenditure already incurred by the board have been committed from the balance of monies allocated to the Area Committee for the Helensburgh Waterfront in 2005/06 and operated on a control account basis by accountancy staff within Strategic Finance.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HELENSBURGH PARTNERSHIP: ESTABLISHMENT AND FUNDING SUPPORTReport 115 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 18 attended
AM
Councillor Alastair McKinlayMember, expected
AM
Councillor Allan MacaskillChair, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksVice-Chair, expected
GF
Councillor George FreemanMember, expected
GH
George HarperOfficer, expected
AH
Councillor Alison HayMember, expected
DH
Douglas HendryOfficer, expected
DK
Councillor Daniel KellyMember, expected
DM
Councillor Duncan MacIntyreMember, expected
RM
Councillor Robert MacintyreMember, expected
SM
Susan MairOfficer, expected

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. HELENSBURGH PARTNERSHIP - ESTABLISHMENT AND FUNDING SUPPORTThis decision
  2. Helensburgh and Lomond Area Community Planning Group Report to the Community Planning Partnership Management CommitteeAgreed
  3. Area Committee Appointment to Helensburgh PartnershipAgreed
  4. Establishment of Helensburgh PartnershipNoted

More from Argyll and Bute Strategic Policy Committee

All decisions
MeetingDecisionOutcome
19 Apr 2007 Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... Noted Open
19 Apr 2007 North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... Agreed Open
19 Apr 2007 Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... Noted Open
19 Apr 2007 Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... Agreed Open
19 Apr 2007 Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies