CORPORATE HEALTH AND SAFETY PLAN 2006 - 2007

Noted Committee 1 paper

Strategic Policy Committee noted this item on Thursday 15 June 2006. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Decision To note the contents of Argyll and Bute Council’s Corporate Health & Safety Plan for the period 1 April 2006 to 31 March 2007 (Reference: Corporate Health and Safety Plan 1 April 2006 – 31 March 2007 by Chief Executive, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Strategic Policy Committee

Argyll and Bute Council

Corporate Health & Safety Plan

2006/2007

J McLellan Chief Executive INTRODUCTION This is Argyll and Bute Council’s Corporate Health and Safety Plan for the period 1st April 2006 - 31st March 2007.

The purpose of the plan is to:

(A) Review the position of the council:

Since the formation of the Council the first priority has been to establish a baseline for the health and safety culture of the Council. Through the various restructuring of the Council the approach towards the management of Health & Safety has been revised to reflect the changes. The approach towards the development of the Corporate Health & Safety Plan was revised within the year 2004-05 Corporate Plan and the individual Service’s Plans are now being incorporated into one document. Throughout the past year, quarterly meetings were arranged with the Head of Personnel Services meeting with the Health & Safety Manager and the representatives of the Departments to discuss the progress made on the Corporate and Departmental set objectives. Following each of these meetings, a Quarterly report was prepared for the Chief Executive who discusses this with the Strategic Management Team.

(B) Reaffirm the Council’s goals, values and objectives for health and safety:

In setting the goals and values the Council has established its philosophy for the way in which it manages health and safety and demonstrates the commitment of the organisation to maintaining a safety culture which involves everyone in the organisation working towards a common goal. The objectives were set to enable the Council to move forward towards the level of safety culture described in the Council’s goals and values.

(C) Provide a guide for Directors to enable them to manage health and safety by a planned corporate approach:

Within the previous Corporate Health & Safety Plans, one of the set objectives was for Directors to produce Annual Service Health and Safety Plans. Since 2004-05 The Annual Corporate Health & Safety Plan issued by the Chief Executive, required Directors to identify their Key Departmental Objectives and Targets in relation to Health & Safety issues, and these were incorporated into the Corporate Health & Safety Plan. This approach has resulted in a more Corporate approach with a manageable and measurable methodology. Within the past year, the Institution of Occupational Health & Safety, (IOSH) course ‘Safety for Senior Executives has been provided to the Chief Executive and the majority of Directors and Heads of Service.

(D) Fulfil the requirement of section 2 of the arrangements to the Council’s General Statement of Health and Safety Policy (PER/GEN/1):

The arrangements section of the General Statement of Health and Safety Policy requires the Chief Executive to prepare an annual Health and Safety Plan and this will be maintained and reviewed. Where required, the layout and content of the Corporate Health & Safety Plan will be amended to reflect the Council’s approach towards Health & Safety. Within this year’s plan, the Directors have been asked to use a preferred lay-out of their plan for the year.

Following the Safety for Senior Executives training courses which were provided in February 2006, the General Statement of Health & Safety Policy from the Corporate Policy has been included within this document.

08/06/2006 ARGYLL AND BUTE COUNCIL

GENERAL STATEMENT OF HEALTH AND SAFETY POLICY

It is the policy of Argyll and Bute Council to take all reasonably practical steps to ensure the health, safety and welfare at work of all employees. The Council also acknowledges its responsibilities in respect of persons other than its own employees.

A high standard of health and safety performance is one of the Council’s primary objectives and is recognised as an integral part of service delivery.

This standard will be achieved by:-

(a) creating and maintaining a positive Health and Safety culture which secures the commitment and participation of all employees;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CORPORATE HEALTH AND SAFETY PLAN 2006: 2007Report 270 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 18 attended
AM
Councillor Alastair McKinlayMember, expected
AM
Councillor Allan MacaskillChair, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksVice-Chair, expected
GF
Councillor George FreemanMember, expected
GH
George HarperOfficer, expected
AH
Councillor Alison HayMember, expected
DH
Douglas HendryOfficer, expected
DK
Councillor Daniel KellyMember, expected
DM
Councillor Duncan MacIntyreMember, expected
RM
Councillor Robert MacintyreMember, expected
SM
Susan MairOfficer, expected

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. CORPORATE HEALTH AND SAFETY PLAN 2006 - 2007This decision
  2. Corporate health and safety plan 2008-2011Noted
  3. Corporate health and safety plan 2007/08Noted
  4. Corporate health & safety planNoted
  5. Corporate health and safety plan 2001/2002Approved

More from Argyll and Bute Strategic Policy Committee

All decisions
MeetingDecisionOutcome
19 Apr 2007 Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... Noted Open
19 Apr 2007 North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... Agreed Open
19 Apr 2007 Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... Noted Open
19 Apr 2007 Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... Agreed Open
19 Apr 2007 Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies