A BEST VALUE REVIEW OF THE CURRENT ARRANGEMENTS FOR ROADS DESIGN

Decided Committee 2 papers

Strategic Policy Committee decided this item on Thursday 20 July 2006. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Decision A vote was taken on the Motion and the Amendment. The Motion received 5 votes and the Amendment received 5 votes. On there being an equality of votes, the Chairman used his casting vote for the Motion and the Committee resolved accordingly. (Reference: Joint Report by Director of Development Services and Director of Operational Services dated 19 June 2006 and Bishops Consulting Executive Summary on A Review of the Current Arrangements for Roads Design dated June 2006, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Strategic Policy Committee

ARGYLL AND BUTE COUNCIL STRATEGIC POLICY COMMITTEE 20 JULY 2006 JOINT REPORT BY DIRECTOR OF DEVELOPMENT SERVICES AND DIRECTOR OF OPERATIONAL SERVICES

A BEST VALUE REVIEW OF THE CURRENT ARRANGEMENTS FOR ROADS DESIGN

1. INTRODUCTION

1.1In December 2005, Argyll & Bute Council (the Council) commissioned Bishops Consulting to undertake a comprehensive assessment of the challenges it faces in delivering the infrastructure and transport element of the capital programme, with specific focus on the subsequent work of the Roads Design Team in progressing projects. These challenges include: • Ongoing constraints on expenditure • Slippage/overspend in a number of key capital projects • The need to create a culture across the Council that encourages the capital programme to be delivered to plan • The impact of the separation of the Design Team and Operational Services • Perceptions (potentially misconceptions) of a relatively high management overhead.

1.2The Council agreed that the review would be undertaken in two distinct phases: • the first phase involved assessing the extent of the current issues facing the Council in delivering the infrastructure and transport element of the capital programme • the second phase involved highlighting the relative strengths and weaknesses of different options/arrangements for addressing these challenges in the future, then setting out a route-map for the implementation of the option deemed to maximise Best Value.

1.3Bishops’ final report summarises the findings from both phases of the work. It draws conclusions and makes recommendations about: • capital programme planning and management • capital project planning and management • the management and operation of the Design Team. Bishops’ findings, recommendations and proposed implementation plan are set out in the Executive Summary of their report. This is attached in the annex to this paper. The full 85-page report is available from the Director of Development Services. 2. REVIEW CONCLUSIONS

2.1Bishops conclude that there are a number of early wins in terms of capital programme planning and management, and project management, which would have an immediate beneficial impact on reducing future slippage and/or overspend on individual roads and infrastructure projects. These early wins are seen as helping to build relationships across the Council, both between officers in different services, and between officers and elected members.

2.2There was an initial assumption among some of those consulted that capital projects had slipped solely due to ‘under-performance’ of the Design Team. While Bishops make a focused number of observations aimed at further improving productivity, successful project delivery and team morale, they are comfortable that current performance is competitive in terms of national benchmarks and industry standard productivity levels.

2.3They consider, however, that managing the increase in the volume of work for the Design Team in the short term – followed by a likely reduction in the medium to long term - will prove to be a significant challenge. This comes at a time when the Council is experiencing recruitment difficulties in attracting suitably qualified staff; while the age profile of the Team sees a number of existing staff members reaching normal retirement age (This has been addressed by the Council on the 28th June 2006). Taken together, such developments emphasises the need for more a more systematic and documented approach to business planning and engaging with external consultants (whether public or private sector).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A BEST VALUE REVIEW OF THE CURRENT ARRANGEMENTS FOR ROADS DESIGNReport 76 KB DownloadRead as text
PDF
Executive Summary to be attached to SMT report 20_6_06Report 193 KB Download

At this meeting

Whole meeting

Who was there

0 of 18 attended
AM
Councillor Alastair McKinlayMember, expected
AM
Councillor Allan MacaskillChair, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksVice-Chair, expected
GF
Councillor George FreemanMember, expected
GH
George HarperOfficer, expected
AH
Councillor Alison HayMember, expected
DH
Douglas HendryOfficer, expected
DK
Councillor Daniel KellyMember, expected
DM
Councillor Duncan MacIntyreMember, expected
RM
Councillor Robert MacintyreMember, expected
SM
Susan MairOfficer, expected

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. A BEST VALUE REVIEW OF THE CURRENT ARRANGEMENTS FOR ROADS DESIGNThis decision
  2. 2024-25 Best Value Thematic Review - TransformationAgreed
  3. Argyll and bute council best value audit report 2025Noted
  4. Best Value Improvement Action Plan UpdateNoted
  5. Best Value Improvement Action Plan UpdateAgreed
  6. Best Value Improvement Action Plan UpdateNoted

More from Argyll and Bute Strategic Policy Committee

All decisions
MeetingDecisionOutcome
19 Apr 2007 Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... Noted Open
19 Apr 2007 North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... Agreed Open
19 Apr 2007 Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... Noted Open
19 Apr 2007 Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... Agreed Open
19 Apr 2007 Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies