Decision i) Noted the involvement of the Helensburgh Partnership in taking forward the detail for swimming pool and seafront development as part of their ongoing work programme. ii) That the implications of issues raised during the development phase, with input from the wider community, be brought back to a future meeting of the Helensburgh and Lomond Area Committee after the May 2007 elections with a further report in October 2007. (Reference: Report by Link Director dated 29 January 2007)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The ongoing work to revitalise the Town Centre and Waterfront and the decision on providing a new swimming pool and associated facilities are priorities of this Area Committee and the Council as part of its corporate and area planning process.
1.2This report identifies a time line and process for firming up on the major issues to be identified as part of the work necessary to achieve real progress.
Recommendations
2.1That Members note the involvement of the Helensburgh Partnership in taking forward the detail for the swimming pool and seafront development as part of their ongoing work programme.
2.2That the implications of issues raised during the development phase, with input from the wider community be brought back to the first Business Day for the Helensburgh and Lomond area after the May 2007 elections with a further Committee Report in October 2007.
3. DETAIL
3.1The Council has accepted as part of the Corporate Plan both the revitalisation of Helensburgh Waterfront and Town Centre and the replacement and enhancement to community facilities in Helensburgh and Lomond as part of the Council’s priorities.
3.2In addition, the Council has made commitment to the Helensburgh Partnership, probably for a period of a further two years (dependent on budget), to act as a conduit for shared input between the Council, Scottish Enterprise Dunbartonshire and the local community to best reflect a shared approach to how investment in the area should be directed.
3.3Members of the Council have previously received an update on the legal position at Helensburgh Pier site and a likely timescale for this being resolved. Members will also be aware of the likely finalisation of the local plan towards October this year.
3.4In order to best reflect the joint approach envisaged by the Helensburgh Partnership it is suggested that this Area Committee request the Partnership to:
1. Participate fully in the development of a brief for the seafront area, bearing in mind the concurrent work now being done on Council office accommodation which is due to be finalised by the end of March this year. 2. That the Executive Director of the Helensburgh Partnership uses the type of model and broad approach suggested by the Yellowbook study and further feedback he has had and will gather from organisations in the town to draft an initial development brief by Sept 2007, which work will be accompanied by input from elected members and officials of this Council. 3. That in particular regard to the provision of a new swimming pool and associated facilities that the Helensburgh Partnership consider the linkages between community aspirations for better facilities and the Council’s core need for a public swimming facility. 4. That in regard to the swimming pool that its preferred location on the Helensburgh Waterfront is borne in mind, but potential links to other ongoing developments in the area are also considered. 5. This in investigating the provision of any new facilities that the Executive Director of the Helensburgh Partnership consults fully with Council staff, both at a Service Head and Facility Management level. 4. CONCLUSION
4.1The necessary work to plan for development of the Helensburgh Seafront and replacement of community facilities needs as wide a consensus as possible together with a major amount of preliminary work to ensure the development brief allows achievable timescales and resources to be identified. This preliminary report allows Members to give their approval for the Helensburgh Partnership to take forward much of the pre- planning necessary to achieve that consensus.
5. IMPLICATIONS
Policy: The report takes forward the Council’s Corporate Planning process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.