Decision Agreed that in the event of the new school facility being certified as meeting the Authority’s requirements and being ready for occupation, and the next service availability date following within the Easter holidays, that a short life Policy Development Group (PDG) be established with full delegated powers to determine any issues arising from such certification. The PDG, if required, would comprise of the Leader, Depute Leader, Spokesperson for Education, Leader of the Liberal Democrat Group, and Leader of the SNP group. (Ref: Report by Director of Community Services dated 22 March 2007, tabled)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
This paper reports on the current position in regard to possible handover of the new NPDO school facility in Rothesay.
Recommendation
It is recommended the Council agree that in the event of the new school facility being certified as meeting the Authority’s Requirements and being ready for occupation, and the next service availability date falling within the Easter holidays, that a short life PDG be established with full delegated powers to determine any issues arising from such certification. The PDG would comprise of five members: the Leader (Chair), Depute Leader, Spokesperson for Education, Leader of the Liberal Democrat Group and Leader of the SNP Group.
3.0DETAIL
3.1Barr have failed to deliver phase 1 of the new Rothesay Joint Campus (RJC) (by the contracted date of 22 December 2006). The Project Agreement (PA) with ABC Schools Ltd states that the next service availability date, being the date on which, if certified complete, the Council would require to take the facility, falls within the Easter holidays, the last day of term being the 30 March 2007 and the first day of term after the Easter holidays being 16 April 2007. There are sensitive contractual issues, which cannot be fully detailed or specified at this time that may result in a claim against the Council.
4.0CONCLUSION
The Council may require, in very early course, to determine issues that may imminently arise from the possible service availability of RJC and it would be prudent to form a PDG with appropriate delegated powers to do so.
5.0IMPLICATIONS
Policy: Nil
Financial: Possible financial implications which require to be determined.
Personnel: Nil
Legal: Possible legal implications which require to be determined.
Director of Community Services 22nd March 2007
Please contact David Logan, QIO Special Projects on 01546 604761
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.