It was agreed that: (a) two proprietary materials be trialled to complete suitable schemes currently in the Capital Programme; and (b) A report be submitted to a future meeting in regard to the outcome of the trials. (Ref: Report by the Area Roads & Amenity Services Manager, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report seeks approval from Members to enter into contracts with two proprietary suppliers up to a value of £50,000 each on proposed works with alternative products on the maintenance road surfaces.
1.2This will enable an evaluation of two alternative products, namely, Colas Ralumac and Ringway Griptex.
Recommendations
2.1To approve that the two proprietary materials be trialled, these trials will be used to complete suitable schemes that are currently in the Capital Programme.
2.2Each of these processes will require up to £50,000.
3. DETAIL
3.1Members should note that other Local Authorities have been using the products. The products are amongst the most versatile road maintenance materials available and provide a micro asphalt thin surfacing.
3.2Both Colas Ralumac and Ringway Griptex can remedy problems such as wheel track rutting and surface deformation by application of a regulating layer followed by a thin overlay.
3.3These materials can be feathered at the edges to minimise accommodation works and due to their reduced thickness will provide greater coverage at less cost. This may reduce their equivalent life when compared with more traditional and expensive methods however in lightly trafficked areas this disadvantage will be outweighed by the significantly greater coverage.
3.4It should be noted that these works are seasonal and if they cannot be completed by mid September then they would require to be carried forward to March.
4. CONCLUSION 4.1 The Council’s obligation to maintain road surfaces and footways in a safe manner remains. Members approval of these trials will allow Argyll & Bute Council the opportunity to assess alternative products with the aim to provide a more cost effective solution for suitable locations.
5. IMPLICATIONS
5.1Policy: Works necessary to comply with the Council Health and Safety Policy 5.2 Financial: None, works carried out from existing budget allocated. 5.3 Personnel: None 5.4 Equal Opportunities: None 5.5 Legal: None
For further information please contact Alan Kerr Roads & Amenity Services Area Manager 01436 658864
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.