Decision The Committee noted the contents of the report by the Director of Operational Services and urged all parties to ensure as swift a completion of the works as possible. (Reference: Report by the Director of Operational Services dated 25 th January 2008 - submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
That the Area Committee notes the contents of the report.
3 BACKGROUND (as reported to SPC November 2006)
3.1This project has had a gestation period of over 15 years. It was originally considered when pontoons were first installed in the Outer Harbour in the early 1990s and a feasibility study was carried out at that time into the possibility of expanding pontoon provision to the Inner Harbour.
This study pointed to the installation of sheet piling below the water level to support the inner harbour walls to allow the requisite dredging to be carried out but without taking away or covering the historic stone walls of the harbour. The proposal was for a transit yacht berthing marina which would bring significant economic and visual benefit to the town centre of Rothesay.
In June 2005 the Strategic Policy Committee authorised the appointment of Scott Wilson Scotland Ltd to carry out the engineering feasibility for a major project to sheet pile, dredge and install a pontoon system for leisure craft in the Inner Harbour at Rothesay. The opportunity had arisen to combine the study with the engineering design process with that about to be carried out for the improvements to the ferry terminal.
3.2It was anticipated throughout the development of the project that Argyll and the Islands Enterprise would make a significant contribution to the project, which when added to the £870,000 in the Council’s Capital Programme, would meet the potential total project cost of circa £1.4 million.
Scott Wilson Ltd reported in March 2006 that the likely total project cost was of the order of £2.5m inclusive of works, design and supervision costs and contingencies. Although this would require more funding than had been anticipated by AIE, it was still keen to pursue its involvement in the project.
3.3Following a development meeting with AIE in May 2006, it was agreed in order to obtain the best possible cost information, that detailed engineering design be completed and the work included in the call for tenders for the Rothesay ferry berth works. This was carried out and an analysis of tenders showed that the estimated total project cost of the inner harbour work based on the lowest tender received was £2.331m.
3.4AIE, reflecting the potential significant impact of the project on the economic regeneration of Bute, in conjunction with its Parent Board, secured the additional funding required through the Scottish Executive and made a grant offer to the Council of £1.501m towards the Inner Harbour project. The combined works for the ferry berth reconstruction and inner harbour were awarded to Balfour Beatty Ltd with a tender value of nearly £10m.
4 CURRENT POSITION
4.1The contract works began in November 2006 on the creation of the new ferry berth infrastructure (linkspan, berthing structures, formation of new berth). Constructional difficulties were experienced in forming the new berthing structures that impacted on the overall works programme.
As a result, although some preliminary work on the Inner Harbour works began in early 2007, meaningful progress was not made until the problems with the berthing structures were resolved.
The contractor’s chosen method of carrying out the Inner Harbour work was to construct a closure between the main pier and the end of the Mid Pier and to pump out the inner harbour to allow him access for the installation of the low level ground anchors.
He encountered further delays due to the difficulty in making the closure sufficiently watertight which required the installation of further temporary piling that allowed the inner harbour to be dewatered and allowed access for his plant and activities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.