Decision 1. In recognition of the importance of the paper and the need for more consideration of the content therein, it was decided to refer this to the June Business Day meeting and on the completion of local consultation to bring it to a future Area Committee meeting. 2. That Members be invited to e-mail any questions they have to officers in order that they can be addressed at the business day meeting. (Ref: Report by Director of Operational Services dated 9 May 2008, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1Members are asked to consider the details of this report and respond with views prior to a committee report being brought to the Council’s Executive in August.
Background
3.1The principle of alternate weekly collection (AWC) trials i.e. fortnightly residual waste collection alternating with recycling/composting collections was approved by the then Strategic Policy Committee on 19 January 2006.
After that, information relating to the proposed trials was brought to the MKI Area Committee in respect of Islay and Jura and the OLI Area Committee for Lismore. In December 2006 these trials were reported on to the Strategic Policy Committee (SPC). The SPC approved the continuation of the trials and that investigation work be carried out to examine the potential for alternate weekly collections firstly on Mull and Iona, Tiree and then Helensburgh and Lomond. Alternate weekly collections were also to be examined in the Shanks PPP contract area once the outcome of the mixed waste composting issue is known.
Once such investigations had taken place, reports were to be prepared and brought to the relevant Area Committees for consideration and a report then submitted to the SPC (as it was called at that time).
Islay /Jura and Lismore trials have continued since then and discussions between Operational Services staff have taken place mainly regarding the potential for AWC in the areas outwith the PPP contract.
There is still some degree of uncertainty regarding the mixed waste composting issue but it now looks more likely that Shanks will use the compost material for landfill restoration. Shanks have contractual landfill diversion targets to meet under the PPP contract, hence the initial AWC focus has been on the non PPP area i.e. Islands and Helensburgh & Lomond. An Oban Lorn and The Isles Area Committee report in respect of AWC for Mull and Iona, Coll and Tiree is being presented in June also.
A report on the Waste Management PPP was presented to the Executive Committee on 17 April 2008.
There have been two reports (dated 13.12.07 and 23.04.08) presented on the alternate weekly collection issue to the Environment Policy and Performance Group (PPG).
The PPG Group on 13.12.07 welcomed the report and the principle of rolling out alternate weekly collections although cautioned that more required to be done in terms of publicising proposals. The Group asked that a Communications Strategy be presented at the April 2008 meeting. A Helensburgh and Lomond draft Communications Strategy is included in Appendix 2.
The issue of kitchen waste relating to AWC was included in the 23.04.08 Environment PPG report. The Group welcomed the principle of potentially carrying out weekly kitchen waste collections.
3.2Reasons for Possible Expansion
The reasons for proposed expansion of alternate weekly collections are as follows:
1. The Scottish Government levies Landfill Diversion Targets on Scottish Local Authorities in line with European UK Landfill Diversion Targets which place yearly limits on biogradeable waste which can be landfilled by the Council. The targets in place become more onerous year on year and if landfill limits are exceeded and penalties are levied as expected, fines on individual local authorities will rise to £150 per tonne in 2009/10.
2. The Scottish Government in January 2008 issued targets of a 40% recycling and composting by 2010 and 50% by 2013. The current Argyll and Bute Council rate is 34%. (This figure includes mixed waste compost currently being stockpiled by Shanks for landfill restoration use). The current waste diversion and recycling rate in the PPP Contract area is around 40%.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.