CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Environment Policy and Performance Group, Wednesday 25 June 2008 at 11.00am

CARBON MANAGEMENT PROGRAMME

Noted Committee 1 paper

Environment Policy and Performance Group noted this item on Wednesday 25 June 2008. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Decision 1. Noted the contents of the report and further noted that the Project Board would provide regular progress reports to the Environmental PPG meetings. 2. That a report be submitted to the PPG in October advising of the outcome of the meeting with the Head of Strategic Finance regarding capital funding for the Carbon Management Programme. 3. To recommend to the Executive Committee that under the implications section of reports submitted to Council Meeting, a “Climate Change” heading be inserted. (Ref: Report by Head of Facility Services dated 25 June 2008, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment Policy and Performance Group

ARGYLL & BUTE COUNCIL ENVIRONMENT PPG

BRIEFING NOTE 25 June 2008

LOCAL AUTHORITY CARBON MANAGEMENT PROGRAMME LAUNCH DATE 3 JULY 2008

1. INTRODUCTION

1.1The internal launch for the Carbon Management Programme will be held at Manse Brae on 3 July. The programme will run until the end of the financial year.

2. PROGRAMME AIMS

2.1The aims of the programme can be summarised as:

2.1.1 Establishing the Council’s baseline carbon and green house gas emissions 2.1.2 Identifying a target for reducing these emissions and associated savings in revenue expenditure 2.1.3 Identifying the opportunities to make savings and subjecting them to Business Case Evaluation 2.1.4 Establishing a programme for delivering the savings 2.1.5 Developing a long term strategy to manage future emissions and reduce future financial and environmental risk exposure to the Council from potential rising energy costs and statutory obligations.

3. PROJECT BOARD

3.1The composition of the Project Board is attached. The indicative Project Plan is attached.

3.2The Project Board will be asked to endorse the draft Project Plan and the proposed emission reduction target for the Council at its first meeting on 3 July 2008. 4. EMISSIONS REDUCTION TARGET

4.1At the launch of the LACM scheme for 2008/9, the Carbon Trust advised participants that 5–10 year targets of savings of between 20-30% would not be untypical. Experience to date has shown that those participants who have set more exacting targets at the outset of the programme have proved to be the most successful at reducing carbon and green house gas emissions.

4.2As points of reference, the Highland Council has set a target of a 15% reduction in emissions.

4.3In preparing documentation for the Internal Launch event, the Energy Management Team will propose to the Project Board that Argyll & Bute Council should set a target of reducing its carbon emissions by 20% from the 2007/8 level by the end of 2013/14.

4. PROGRESS REPORTING

4.1The Project Board will provide regular progress reports to the Environmental PPG

Sandy Mactaggart Head of Facility Services 25 June 2008 Local Authority Carbon Management Programme Internal Kick-off

Argyll and Bute Council

Date; Thursday 3rd July 2008

Time; 10:00hrs (Tea/Coffee available from 09:30hrs)

Location Address; Argyll and Bute Council Offices, 1A Manse Brae, Lochgilphead, PA31 8RD – Ground Floor Conference Room

Attendee Name Role

PROGRAMME BOARD

John Semple Councillor Sponsor Sandy Mactaggart Project Sponsor Paul Gillies Project Leader Margaret Moncur Finance Champion Audrey Martin Executive Malcolm MacFadyen Executive Joanna Miller Executive

Launch Attendees

Alison Hay Executive Andy Law Executive John Dowell Carbon Insight Programme Advisor - Change Matthew Brander Carbon Insight Programme Advisor - Technical Jennifer Swanson Team member – Strategy Neil Leckie Team member – Asset Mgt/Property Peter Robinson Team member – Fleet Tom Kerr Team member – Waste/Mileage Nicola Debnam Team member – Transport Strategy Alan Millar Team member – Waste Ryan McGlynn Team member - Streetlighting Linda Syed Team member - Communications Alan Brough Team member – Procurement Gerry Wilson Team member – IT Alison McVicar Team member – Energy Peter Cupples Executive Annex C – Generic Milestone Chart – to be tailored to YOUR timescale May June July August September October November December January February March Milestone / Event / Activity Owner 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 3 10 17 24 31

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CARBON MANAGEMENT PROGRAMMEReport 84 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 10 attended
DB
Donald BrownOfficer, expected
GC
Councillor Gordon ChalmersMember, apologies
RC
Councillor Rory ColvilleMember, present
MD
Councillor Mary-Jean DevonMember, apologies
AH
Councillor Alison HayMember, present
DK
Councillor Daniel KellyMember, present
SM
Shirley MacLeodSecretary, expected
BM
Councillor Bruce MarshallMember, present
AR
Councillor Al ReayMember, present
JS
Councillor John SempleChair, present

On this subject at Argyll and Bute

Search all
  1. CARBON MANAGEMENT PROGRAMMEThis decision
  2. Carbon management: wind turbine at glengorm landfill site updateNoted
  3. Carbon management business cases 2013/14Approved
  4. Carbon management plan (2009 - 2014) - 2011 updateNoted
  5. Carbon management plan implementationNoted
  6. Carbon management planAgreed

More from Argyll and Bute Environment Policy and Performance Group

All decisions
MeetingDecisionOutcome
27 May 2010 Road verges action planDecision Agreed to recommend to the Executive that the following points be given due consideration when considering t... Agreed Open
27 May 2010 Consultation: draft marine nature conservation strategy for scotland and scottish marine protected areas guidelinesDecision 1. That the Marine and Coastal Development Manager contact the Scottish Government to establish timescales f... Noted Open
27 May 2010 Grounds maintenance savings planDecision 1. The PPG recorded their disappointment that this paper was not available for discussion and their concerns... Decided Open
27 May 2010 ScorecardsDecision Agreed that an alert from Pyramid be issued to Environment Thematic CPP Group Members on a monthly basis. (R... Agreed Open
25 Feb 2010 Green charter awardDecision The PPG agreed that in principle this scheme had potential to be rolled out to departments although they req... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies