Environment Policy and Performance Group noted this item on Wednesday 25 June 2008. Below is the council's own wording, with the papers it was decided on.
Decision 1. Noted the contents of the report and further noted that the Project Board would provide regular progress reports to the Environmental PPG meetings. 2. That a report be submitted to the PPG in October advising of the outcome of the meeting with the Head of Strategic Finance regarding capital funding for the Carbon Management Programme. 3. To recommend to the Executive Committee that under the implications section of reports submitted to Council Meeting, a “Climate Change” heading be inserted. (Ref: Report by Head of Facility Services dated 25 June 2008, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment Policy and Performance Group
ARGYLL & BUTE COUNCIL ENVIRONMENT PPG
BRIEFING NOTE 25 June 2008
LOCAL AUTHORITY CARBON MANAGEMENT PROGRAMME LAUNCH DATE 3 JULY 2008
1. INTRODUCTION
1.1The internal launch for the Carbon Management Programme will be held at Manse Brae on 3 July. The programme will run until the end of the financial year.
2. PROGRAMME AIMS
2.1The aims of the programme can be summarised as:
2.1.1 Establishing the Council’s baseline carbon and green house gas emissions 2.1.2 Identifying a target for reducing these emissions and associated savings in revenue expenditure 2.1.3 Identifying the opportunities to make savings and subjecting them to Business Case Evaluation 2.1.4 Establishing a programme for delivering the savings 2.1.5 Developing a long term strategy to manage future emissions and reduce future financial and environmental risk exposure to the Council from potential rising energy costs and statutory obligations.
3. PROJECT BOARD
3.1The composition of the Project Board is attached. The indicative Project Plan is attached.
3.2The Project Board will be asked to endorse the draft Project Plan and the proposed emission reduction target for the Council at its first meeting on 3 July 2008. 4. EMISSIONS REDUCTION TARGET
4.1At the launch of the LACM scheme for 2008/9, the Carbon Trust advised participants that 5–10 year targets of savings of between 20-30% would not be untypical. Experience to date has shown that those participants who have set more exacting targets at the outset of the programme have proved to be the most successful at reducing carbon and green house gas emissions.
4.2As points of reference, the Highland Council has set a target of a 15% reduction in emissions.
4.3In preparing documentation for the Internal Launch event, the Energy Management Team will propose to the Project Board that Argyll & Bute Council should set a target of reducing its carbon emissions by 20% from the 2007/8 level by the end of 2013/14.
4. PROGRESS REPORTING
4.1The Project Board will provide regular progress reports to the Environmental PPG
Sandy Mactaggart Head of Facility Services 25 June 2008 Local Authority Carbon Management Programme Internal Kick-off
Argyll and Bute Council
Date; Thursday 3rd July 2008
Time; 10:00hrs (Tea/Coffee available from 09:30hrs)
Location Address; Argyll and Bute Council Offices, 1A Manse Brae, Lochgilphead, PA31 8RD – Ground Floor Conference Room
Attendee Name Role
PROGRAMME BOARD
John Semple Councillor Sponsor Sandy Mactaggart Project Sponsor Paul Gillies Project Leader Margaret Moncur Finance Champion Audrey Martin Executive Malcolm MacFadyen Executive Joanna Miller Executive
Launch Attendees
Alison Hay Executive Andy Law Executive John Dowell Carbon Insight Programme Advisor - Change Matthew Brander Carbon Insight Programme Advisor - Technical Jennifer Swanson Team member – Strategy Neil Leckie Team member – Asset Mgt/Property Peter Robinson Team member – Fleet Tom Kerr Team member – Waste/Mileage Nicola Debnam Team member – Transport Strategy Alan Millar Team member – Waste Ryan McGlynn Team member - Streetlighting Linda Syed Team member - Communications Alan Brough Team member – Procurement Gerry Wilson Team member – IT Alison McVicar Team member – Energy Peter Cupples Executive Annex C – Generic Milestone Chart – to be tailored to YOUR timescale May June July August September October November December January February March Milestone / Event / Activity Owner 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 3 10 17 24 31
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment Policy and Performance Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Grounds maintenance savings planDecision 1. The PPG recorded their disappointment that this paper was not available for discussion and their concerns...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.