Decision 1. To note the contents of the report; 2. To request that a further report detailing the rationale and thought processes behind the scoring of all options be prepared and presented to the next meeting of the Project Board before any decision is taken; 3. To note that Financial appraisal on the recommended options contained within this report will commence and will be due for completion by July 2009. However, the Project Team may undertake further financial appraisals on other options if required, following discussion of the further report detailing rationale of scoring of all options; 4. To note that a presentation will made to the Project Board explaining the process followed in scoring of all options; and 5. To agree that consultation with Community Care Fora should be undertaken to seek their views on criteria used for short-listing of options. (Reference: Report by Director of Community Services, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1. The Project Board previously agreed that the ongoing review of Older Peoples Services should be undertaken in line with the HM Treasury Green Book (TGB). This would include the following stages:
o Justifying the need to undertake the review; o Setting detailed objectives for the desired outcomes of the review; o Carrying out an options appraisal to identify possible solutions which meet the objectives; o Developing and implementing the preferred solution; and o Evaluating the effectiveness of the solution when it has been implemented.
Stage 1: Justifying Action
2. With regard to the first stage the Board noted that the Council’s Executive at its meeting on 20 September 2007 formed the Special Committee and Project Board to review Older Peoples Services. This decision was based on a report to the Executive which clearly noted that the Service Plan for Older People agreed in 2005 by the Argyll and Bute Partnership, identified a need for an estimated increase in resources of £5m per annum in order to meet the anticipated future demand for Care Home places and the social work scrutiny review undertaken in 2006 recommended that the Council should consider externalisation of some of its services. This constituted the justification for undertaking the review.
Stage 2: Setting Objectives
3. In order to comply with the requirements of the TGB detailed objectives should be set for the desired outcomes of the review. The Project Team were tasked with developing the project objectives and this was achieved in a workshop session on 18 July 2008 facilitated by Ernst and Young.
4. Having regard to the nature of the service and the national and local framework in which the service is required to operate, the Team identified the need for a balanced set of objectives that would meet the requirements of delivery of the service, the quality of that delivery, financial sustainability, administrative efficiency and acknowledging perceived future pressures. Having regard to the requirements identified the Team then, through discussion and application of professional judgement, generated a set of objectives that are relevant to the environment in which the service operates. The objectives identified by the Team, along with their respective weightings, are attached in Appendix 1.
5. The objectives identified by the Team were reported to the Project Board on 13 August 2008. After consideration of these the Board adjusted the objectives and the weightings to those contained in Appendix 2 hereof.
Created by Neevia Document Converter trial version http://www.neevia.com Created by Neevia Document Converter trial version 6. The Board tasked the Team to move to identifying and short listing various options for service delivery. The Board requested that once a short list of options was identified by the Project Team they would be agreed by the Board and then these should be subject to detailed appraisal.
Stage 3: Generation and appraisal of options
7. The Team followed an accepted practice used by Ernst and Young in the conduct of other options appraisals undertaken by them which is in accordance with the general guidance provided by the TGB.
Long Listing
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Market test: previous market test 2011Decision The Committee noted the detail of the report. (Report by Executive Director – Community Services dated Janua...
Update on eadar glinn care home, obanDecision The Committee agreed to - 1. Note the content of the report. 2. Undertake a market test as outlined in the d...
Update on struan lodge care home, dunoonDecision The Committee noted the cost analysis with respect to Struan Lodge, noted the excess capacity in the indepen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.